Alternative Public Works Contracting Procedures Sunset Review
Legislative Auditor's Conclusion:
The Legislature should continue the alternative public works
contracting statute. Alternative delivery methods are widely used, and CPARB has
created a forum for stakeholders to continually improve project delivery.
December 2020
In 1991, the Legislature authorized the use of alternative public works contracting
methods for the Department of Corrections. Since then, the Legislature has repeatedly
expanded this authority to include more public bodiesThe public owner of a project, such as the state, a school
district, or a municipality. and project sizes.
The 2013 Legislature reauthorized RCW 39.10 with a sunset provision. The authority to
use alternative contracting methods is scheduled to terminate in June 2021 unless the
Legislature reauthorizes it.
Using alternative contracting methods is an accepted practice nationally
The traditional method of contracting for public works projects is
called Design-Bid-Build. Public bodies select construction contractors based on the
lowest responsive bidA bid that
meets the requirements of the bidding documents. from a responsible
bidder. RCW 39.04.350 specifies criteria for a responsible bidder, including having a
certificate of registration and not being disqualified from bidding on public works
projects.
RCW 39.10 authorizes three alternative contracting methods: Design-Build, General
Contractor/Construction Manager (GC/CM), and Job Order Contracting (JOC). Alternative
public works contracting allows public bodies to select contractors based on
qualifications and price factors.
Along with Washington, the federal government and all other states allow public
bodies to use some type of alternative contracting methods.
Stakeholders and experts report advantages to using alternative methods
JLARC staff conducted 40 interviews with stakeholders over the course of this review.
Stakeholders reported a number of potential advantages to using alternative
contracting methods, including participation of contractors during design, fewer
conflicts, and stronger relationships and teamwork between owners, contractors, and
architects.
Some individuals reported limitations to the alternative delivery methods, such as
GC/CM's criteria for selecting subcontractors, that potentially could be addressed
through statutory changes or by following best practices.
The Capital Projects Advisory Review Board has worked to improve public works
contracting
Statute directs the Capital Projects Advisory Review Board (CPARB) to evaluate public
works contracting and provide policy advice to the Legislature. CPARB has engaged
stakeholders, conducted studies, recommended policy changes to the Legislature,
developed best practices guidelines, and appointed experienced members to the Project
Review Committee.
The Board's Project Review Committee maintains a thorough process for approving
projects and certifying public bodies
CPARB's Project Review Committee (PRC) was established in statute and makes decisions
on public bodies' applications to use certain alternative methods. The Committee has
maintained a consistent application review process across the state.
There have been some gaps in data collection and record keeping
Statute directs the Department of Enterprise Services (DES) to provide staff support
to CPARB and its committees. Some meeting minutes and agendas have not been
consistently recorded or posted to a public website. CPARB, the PRC, and DES have
stated they intend to address these issues.
Public bodies using JOC are required to report specific metrics to CPARB each year.
There have been gaps in data collection and some of the statutory reporting
requirements may not align with CPARB's primary duties or interests.
CPARB has acted on two of three previous JLARC recommendations
In JLARC's 2013 sunset review of alternative methods, the
Legislative Auditor recommended continuing the alternative delivery methods. The
Legislature reauthorized RCW 39.10 and established a new sunset date of June 2021.
The Legislative Auditor also made three recommendations to CPARB regarding data
collection. CPARB has implemented or is in the process of implementing two of the
three:
It has refocused its data collection efforts. Instead of attempting to compile a
quantitative database, CPARB is collecting information that will help it make policy
recommendations.
It has begun collecting information on GC/CM subcontractor awards and
payments.
It has not revised JOC reporting to clearly identify separate contracts with the
same contractor during the annual reporting period.
Legislative Auditor Recommendations
The Legislative Auditor makes two recommendations:
The Legislature should continue the alternative contracting methods in RCW
39.10.
CPARB should evaluate which JOC data it needs to perform its functions and propose
appropriate modifications to the Legislature.
CPARB and DES concur with these recommendations. You can find additional information in Recommendations.
Committee Action to Distribute Report
On December 7, 2020 this report was approved for distribution by the Joint Legislative Audit and Review Committee.
Action to distribute this report does not imply the Committee agrees or disagrees with Legislative Auditor recommendations.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Report Details
1. Alternative contracting is an accepted practice nationally
Using alternative contracting methods is an accepted practice
nationally
The traditional method of contracting for public works
projectsA construction, alteration, repair, or
improvement project funded by a public body. is called
Design-Bid-Build. RCW 39.10 authorizes three alternative contracting methods:
Design-Build.
General Contractor/Construction Manager (GC/CM).
Job Order Contracting (JOC).
Traditional public works contracting requires the selection of a contractor based on
price
In traditional public works contracting, a public bodyThe public owner of a project, such as the state, a school
district, or a municipality. hires an architecture or engineering
firm to design a project. Once the design is complete, the public body solicits bids
from general contractors to construct the project. This method is known as
Design-Bid-Build (DBB). Public bodies select the designer based on qualifications and
the construction contractor based on price—the lowest responsive
bidMeets the requirements of the bidding
documents. from a responsible bidderRCW 39.04.350 specifies criteria for a responsible bidder,
including having a certificate of registration and not being disqualified from
bidding on public works projects..
Alternative public works contracting allows public bodies to select contractors
based on qualifications and price factors
Unlike traditional public works contracting, which separates design and construction
into distinct phases, Design-Build and GC/CM integrate design and construction. This
enables the designer to draw on the contractor's expertise, identify potential design
problems, and propose solutions. Stakeholders report this is particularly valuable on
large, complex projects with unknown risks. All public bodies must comply with
prevailing wage laws and other public works requirements regardless of the contracting
method they use.
Design-Build allows a public body to select one firm to design and construct a
project
A public body selects a single entity, the design-builder, to perform the entire
project from design through construction, based on qualifications and price-related
factors. A design-builder is typically a team of a general contractor and a design
firm, assembled for a specific project.
There are several varieties of design-build contracts. In one, public bodies may
select a design-builder based on a design package and price proposal. In another, they
may select a design-builder based on qualifications, technical approach, and price
factors. This latter alternative is known as progressive design-build. It allows the
public body to participate more fully in the project's design and is less costly for
design-builders to prepare a proposal. The total contract amount is negotiated between
the public body and design-builder.
General Contractor/Construction Manager (GC/CM) allows a public body to contract
with a design firm and a general contractor
A public body contracts with an architecture or engineering firm as they would under
traditional public works. Early in the project, the public body can select a general
contractor based on qualifications and factors that will influence cost, such as
contractor fees. The contractor then provides input on the design. When the design is
at least 90% complete, the public body and the contractor negotiate the maximum allowable construction cost (MACC)The maximum cost of the work to construct the project, including a percentage for
risk contingency, approved change orders, and support services, such as surveying
and cleanup.. The public body retains a separate contract with the
design firm.
Exhibit 1.1: The timing of contractor selection varies by delivery method
Source: JLARC staff analysis of RCW 39.04 and RCW 39.10. Graphic shows progressive
design-build. In other types of design-build, design-builders submit more extensive
design proposals as part of the selection process.
Exhibit 1.2: Contractual relationships vary under different delivery methods
Source: JLARC staff analysis of RCW 39.04 and RCW 39.10.
Job Order Contracting (JOC) allows a public body to enter two-year contracts with a
construction contractor for an undefined quantity of work at agreed upon pricing
Instead of soliciting bids for smaller projects, public bodies may use a competitive
process known as JOC to select a contractor who will be on-call to perform multiple
projects over a two-year period. Costs are based on standard published prices for
labor and materials, plus an agreed-upon markup for overhead and services provided by
the contractor. The contractor must subcontract at least 90% of the work.
JOC work orders are limited to projects under $500,000. The contractor can complete
any number of these projects up to $4 million per year for most public bodies, or $6
million per year for the Department of Enterprise Services (DES) and larger cities and
counties. A public body may renew a contract for an additional third year without
rebidding.
Exhibit 1.3: Job Order Contracting allows one contract for multiple projects
Source: JLARC staff analysis of RCW 39.10.
Using alternative contracting methods is a common and accepted practice
nationally
As noted in JLARC's 2013 sunset review, alternative contracting methods are
common in Washington and nationally. The Legislature first authorized alternative
methods in 1991 and has steadily expanded this authority since. More public bodies are
eligible to use alternative methods now than in the past, there are lower minimum
thresholds for project costs, and limits on the allowable number of projects have
increased or, in some cases, been removed.
Since 2013, hundreds of projects have been completed using alternative methods. It is
not possible to provide an exact number of projects and users in Washington because
not all approved projects move to construction and not all public bodies are required
to report their use. In addition, some agencies have their own separate statutory
authority for alternative contracting, such as the Washington State Department of
Transportation.
Although it is not currently possible to establish a precise number, public bodies
report using or planning to use alternative procedures on at least $2 billion in
public works construction each year. Meanwhile, public bodies report about $6 billion
in total public works construction each year, including both alternative and
traditional public works.
The federal government and all 50 states allow some alternative contracting
methods
While the authorized methods vary by state and at the federal level, alternative
contracting methods are common and widespread. For example, federal agencies are
widely permitted to use Design-Build. State agencies in 44 states and Washington, DC
also are widely permitted to use Design-Build. In the six other states, state agencies
have more limited or extremely limited authority to use it.
Stakeholders and experts report advantages to alternative contracting
JLARC staff conducted 40 interviews with stakeholdersPublic bodies, contractors, architects, and
experts. over the course of this review. Stakeholders reported a
number of potential advantages to using alternative contracting methods as compared to
traditional public works contracting. The most common reported advantages are that:
The contractor selection method and timing are more flexible. For example:
Under Design-Build and GC/CM, contractors are brought onto the project earlier
during the design phase, rather than after the design is complete.
Under Design-Build and GC/CM, contractors are selected based on qualifications
rather than the lowest responsive bid from a responsible bidder.
Under Design-Build, subcontractors can be selected at any time in the project
based on their qualifications or other criteria.
Under GC/CM, some subcontractors can be brought in during the design phase
based on their qualifications.
There are typically fewer conflicts and/or change orders.
The public body, architect or engineer, and contractor have increased
opportunities to form relationships and work as a team.
Exhibit 1.4: Reported benefits of using alternative contracting methods
Source: Interviews with study participants.
Some stakeholders cited limitations to the alternative methods or related statutory
requirements
Although overall feedback from stakeholders was positive, some individuals reported
limitations that potentially could be addressed through statutory changes or by
following best practices.
For GC/CM projects:
Construction subcontractors are selected based on price rather than
qualifications. Currently, electrical and mechanical subcontractors can be
selected during the design phase based on the firm's qualifications. Some
stakeholders recommended expanding this option to other subcontractor trades.
Subcontractor bonding requirements may prevent small subcontractors from
participating. Stakeholders report that this is an additional cost for public
bodies, that it is inefficient, and that it may limit participation of disadvantaged
business enterprises. Traditional public works and design-build projects do not
require subcontractor bid and payment bonds and private industry often allows the
use of other insurance products instead of bonds.
For design-build projects:
The design firm typically works for the construction contractor rather than the
public body. This requires the public body to manage the project without
having the contracted design firm as the owner's representative.
In traditional design-build, the solicitation process can be expensive, and
total contract price is set during the procurement phase when there are still a
lot of uncertainties. The public body may have limited involvement in the
design. Progressive design-build addresses some of these limitations, but it can be
challenging for new firms to win alternative contracts.
For all alternative construction projects:
Alternative methods emphasize teamwork and fast decision making, which can be
challenging for a public body with limited experience using alternative
contracting methods.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Report Details
2. CPARB complies with statute
The Capital Projects Advisory Review Board (CPARB) has worked to
improve public works contracting in Washington
Statute established the Capital Project Advisory Review Board (CPARB) to evaluate
public works contracting and provide policy advice to the Legislature. CPARB has 19
voting members, 15 of whom are appointed by the governor and four of whom are
appointed by other bodies. There are also four nonvoting members from each of the
major legislative caucuses.
CPARB has developed and recommended policy changes to the Legislature
Statute directs CPARB to develop and recommend policies to enhance the quality,
efficiency, and accountability of public works construction. This may include
expanding, modifying, or eliminating alternative public works contracting methods.
Since 2013, CPARB has developed and recommended five bills. Two additional bills were
introduced based on the work of CPARB or its committees. Five of these seven were
enacted into law. The changes included:
Job Order Contracting (JOC) expansion. In 2013, HB 1466 increased the
annual limit of contracts to $6 million for counties with populations greater than
one million. In 2019, SHB 1295 expanded JOC authority to all public bodies in
Washington and increased the contract and award limits.
Heavy Civil General Contractor/Construction Manager (GC/CM). In
2014, HB 2208 authorized the use of GC/CM on heavy civil infrastructure projects,
such as sewers, roads, bridges, and tunnels. GC/CM firms managing heavy civil
projects were authorized to perform more of the work themselves.
Progressive Design-Build authority. In 2019,SHB 1295 authorized
Progressive Design-Build, which reduces the cost of submitting proposals for
Design-Build projects and enables greater owner participation in the design.
Inclusion and apprenticeship requirements. In 2019, SHB 1295 required that
design-builders submit plans for inclusion of underutilized firms—such as firms
owned by women, minorities, or veterans—as subcontractors or suppliers. It also
required that job order contractors use apprenticeship programs on large work
orders.
CPARB has studied and shared public works information with the Legislature and
stakeholders
CPARB has begun or completed studies and submitted reports to the Legislature on
public works issues. Topics include:
Life cycle cost analysis and energy efficiency (submitted to the Legislature in
2013).
Local government public works methods, including the small
works roster proceduresProcedures that may be used on
projects under $350,000. and the limited
public works processAn alternative process for projects
under $50,000. (requested by ESSB 5418 in 2019 and still in
progress).
Subcontractor listing policies and practices (requested by ESB 5457 in 2020 and
still in progress).
Best practice guidelines for using Design-Build (published in 2018) and guidelines
for using GC/CM and JOC (still in progress).
CPARB has appointed experienced members to its committees and engaged stakeholders
in its work
Statute directs CPARB to appoint knowledgeable people to the Project Review Committee
(PRC), which makes decisions on whether to approve applications from public bodies to
use the Design-Build and GC/CM methods. CPARB's process to appoint PRC members
includes an application, a public consideration, and a vote.
CPARB is also authorized by statute to form additional committees as needed. There
are currently 10 CPARB committees in addition to the PRC. Committee members include
representatives from 29 private businesses, 19 public bodies or public owner
associations, four labor organizations, and three private associations.
CPARB has acted on two of three previous JLARC recommendations
In 2013, the Legislative Auditor made three recommendations to CPARB. The Board has
implemented or is in the process of implementing two of these, and has not
implemented one.
CPARB has refocused its data collection efforts on project delivery
methods. In 2013, JLARC staff found that CPARB had attempted to assemble a
database of project information, but the data was not comprehensive or reliable. The
Legislative Auditor recommended that CPARB refocus its efforts to collect
information that would more readily help it evaluate public works delivery methods.
CPARB has done so.
CPARB has begun to collect information on GC/CM subcontractor awards and
payments. Statute requires that general contractors perform no more than 30%
of the maximum allowable construction costThe maximum cost of the work to construct the project,
including a percentage for risk contingency, approved change orders, and support
services, such as surveying and cleanup. for GC/CM projects,
with the exception of heavy civil projects. In its 2013 sunset review, JLARC staff
found that the information needed to document compliance with this requirement was
dispersed and unorganized. The Legislative Auditor recommended that public bodies
document this information and CPARB has begun collecting it through the PRC review
process.
CPARB has not revised JOC reporting to reduce the appearance of noncompliance.
The 2013 review noted that JOC reporting forms could give the appearance of
noncompliance with statutory contract limits because of the way JOC data was
aggregated. The Legislative Auditor recommended that CPARB revise JOC reporting to
more accurately identify individual contracts in place during the reporting
period.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Report Details
3. Project Review Committee is thorough in its reviews
The Project Review Committee maintains a thorough process for
approving projects and certifying public bodies
The Project Review Committee (PRC) uses a thorough and consistent process for making
decisions on applications to use alternative methods
The PRC is a committee of the Capital Projects Advisory Review Board (CPARB). Members
are appointed by CPARB and represent public bodies and industry stakeholders.
Statute directs the PRC to evaluate and make decisions on applications from public
owners that want to use the Design-Build and General Contractor/Construction Manager
(GC/CM) methods. Applicants may request approval for individual projects or they may
seek certification to use the methods at their own discretion for a period of three
years.
Public bodies may want to seek three-year certification if they expect to complete a
large volume of alternative public works projects. Examples of public bodies that have
received certification include the Department of Enterprise Services, University of
Washington, and Sound Transit.
The PRC evaluates whether applicants meet statutory criteria
Applicants must submit a formal application to the PRC and make a public
presentation. The public has an opportunity to comment on the application before there
is a public deliberation and vote by the PRC members.
For all applications, the PRC evaluates whether applicants have the capacity and
experience to use alternative contracting methods successfully and whether they have
resolved any previous audit findings.
For project applicants, the PRC evaluates whether the project meets
statutory criteria for using an alternative method, such as a construction project
at a hospital or school that will be occupied and operating during construction or a
project that requires specialized work on a historical building. See Appendix
B for a full list of the statutory criteria (RCW 39.10.280, RCW 39.10.300, and
RCW 39.10.340). Applicants must also demonstrate that using Design-Build or GC/CM
will provide a substantial fiscal benefit or that the traditional delivery method is
not practical.
For certification, a public body must demonstrate success in managing both
traditional and alternative public works projects and the necessary experience to
determine when it is appropriate to use alternative contracting methods.
For recertification, a public body must document its success in managing
alternative public works projects for three years before it can seek recertification
for an additional three years. Applicants must summarize how their projects have met
statutory criteria for using alternative delivery methods.
Since 2013, the PRC has approved 179 projects and 38 certifications or
recertifications
Between 2013 and June 2020, the PRC approved 51 applications to use Design-Build and
128 applications to use GC/CM for specific projects.
During this same time period, the PRC approved 13 applications for certification and
25 applications for recertification. There are currently 13
public bodiesSome public bodies have applied more than
once during the review period, and some have applied for more than one method.
Some public bodies have not sought recertification. certified to use
Design-Build, GC/CM, or both. See Appendix A for a list of certified public bodies and
approved projects.
Exhibit 3.1: Map of Design-Build and GC/CM projects approved and public bodies
certified since 2013
Source: JLARC staff analysis of PRC records.
Exhibit 3.2: More than $23 billion of projects have been approved by or reported to
the PRC since 2013
Source: JLARC staff analysis of PRC records. Amounts include individual projects
approved by the PRC as well as projects reported to the PRC by certified public
bodies.
PRC has denied applications for projects, certifications, and recertifications
Since 2013, the PRC has denied 10 applications for project approval and 3
applications for agency certification or recertification. The most common reason for
denial is that the public body's development team lacks experience with alternative
public works contracting methods.
Public bodies are responsible for complying with statute
Similar to traditional public works projects, public bodies using alternative
construction methods are responsible for complying with the statutory requirements
related to the particular methods they use. The PRC does not monitor projects during
construction and is not responsible for ensuring that public owners are in compliance
with public works statutes.
All public bodies are accountable to their citizens and stakeholders, subject to
audit by their local governments and the State Auditor’s Office. They are open to
litigation if they are out of compliance.
If deficiencies are brought to their attention, CPARB and the PRC can limit a public
body’s future use of Design-Build or GC/CM in one of two ways:
Revoke certification. The PRC may revoke a public body's certification if
it finds that its use of Design-Build or GC/CM no longer serves the public interest.
For individual projects, there is no power to revoke approval.
Deny future project applications. If a public body does not comply with
statutory requirements on a public works project, the PRC may reject a future
application by the body to use alternative methods.
Unlike Design-Build and GC/CM, Job Order Contracting (JOC) does not require PRC
approval. The PRC cannot approve, deny, or revoke a public body’s use of JOC.
JLARC's review of a sample of projects indicates general compliance with the GC/CM
self-performance limit
JLARC staff reviewed a sample of projects for compliance with the statutory
requirement that general contractors on GC/CM projects perform no more than 30% of the maximum allowable construction costWith the exception of heavy civil projects..
The remainder of the work must be performed by subcontractors.
To assess whether contractors were complying with the self-performance limits, JLARC
staff examined subcontractor awards and payments for projects completed by 11 of the 12 public bodiesThe University
of Washington could not supply the necessary records to facilitate our
review. certified to use GC/CM and a sample of non-certified public
bodies. Of the 40 projects we reviewed, 38 complied with the self-performance limit,
while 2 exceeded the self-performance limit by 0.03 and 0.67 percentage points.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Report Details
4. There are some gaps in data collection and record keeping
The Department of Enterprise Services provides staff support to
CPARB. Over the years, there have been some gaps in data collection and record keeping.
Statute directs the Department of Enterprise Services (DES) to provide staff support
to the Capital Project Advisory Review Board (CPARB), the Project Review Committee
(PRC), and other CPARB committees.
In fiscal year 2020, DES budgeted 0.85 FTE for staff support, including 0.75 for
administrative support and 0.1 FTE for professional staff oversight. As part of its
support role, DES performs administrative tasks for the board and its committees.
Board and committee activities are public and transparent, but some practices were
not compliant with the Open Public Meetings Act
Washington's Open Public Meetings Act (RCW 42.30) requires that all public boards and
committees deliberate and take actions in a public setting. Meeting minutes must be
recorded and made available, schedules must be published in advance, and agendas must
be posted online.
Although DES posts information about CPARB, the PRC, and other committees on CPARB's
website, JLARC staff identified several lapses in record keeping:
Since 2017, PRC meeting minutes have not been consistently recorded, approved, or
made available. DES has made audio recordings of meetings and is having them
transcribed.
Some of CPARB's other committees have not consistently recorded meeting minutes or
made schedules or agendas publicly available.
CPARB, the PRC, and DES are aware of these issues and have stated that they intend to
address them.
There are gaps in JOC data collection and record keeping
Statute requires public bodies that use Job Order Contracting (JOC) to report the
following metrics to CPARB each year:
A list of work orders issued.
The cost of each work order.
A list of subcontractors hired under each work order.
CPARB is authorized to request copies of intents to pay prevailing wage and
affidavits of wages paid. CPARB also requests that public bodies using JOC attest to
their compliance with certain statutory provisions and submit information about the
participation of minority-owned, women-owned, veteran-owned, and small businesses.
DES staff are responsible for collecting the data and summarizing it for CPARB’s JOC
Evaluation committee. Over the years, there have been gaps in data collection and
record keeping:
Missing reports. DES staff cannot locate the JOC reports submitted by
public bodies for 2014, 2015, and 2016 and believe they were lost during staff
turnover. In 2017, DES suspended collection of JOC reports due to budget cuts. In
2020, DES resumed collection of the reports from 2017, 2018, and 2019.
Incomplete or inaccurate reports. Some reports included work orders that
were issued and completed outside of the reporting period. Not all public bodies
reported the same data elements.
Overlapping contract years. JOC reports do not clearly identify the length
of each contract or distinguish between multiple contracts with the same contractor
during a reporting period. Without these distinctions, it is difficult to determine
if a contract exceeds statutory limits.
Potential underreporting. Some public bodies may not have submitted the
required JOC reports. Prior to 2019, statute limited use of JOC to certain public
bodies. Statutory changes in 2019 resulted in all public bodies having the authority
to use this contracting method. Because public bodies do not need to apply for
approval, CPARB and DES do not have a mechanism to track which entities are using
JOC and how many entities should be submitting reports each year.
JOC's statutory reporting requirements may not align with CPARB's primary duties or
interests
CPARB's JOC Evaluation Committee is charged with reviewing data collected in JOC
reports, developing best practices for JOC usage, and developing policy
recommendations. It has used some of the data collected from these reports to provide
briefings to CPARB on JOC's overall usage trends. However, much of the information
collected relates to statutory reporting requirements and CPARB has not used this
data.
Statute does not direct CPARB to monitor public bodies for compliance with JOC
requirements. So far, CPARB has indicated it has not had the staff capacity to do so,
and the Board has not expressed an interest in this type of oversight.
As noted in Section 2, CPARB has engaged stakeholders to address issues of concern in
public works contracting. The Board has used other tools and information to develop
and recommend policies to the Legislature for improving the quality, efficiency, and
accountability of public works projects.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Report Details
5. Answers to Sunset questions
CPARB and the PRC have complied with legislative intent. In
general, stakeholders report that termination would have a negative effect on public
works contracting.
Sunset review answers four key questions
1. Has the use of RCW 39.10 complied with legislative intent?
Yes. Public bodiesThe public
owner of a project, such as the state, a school district, or a
municipality. may use Design-Build, General Contractor/Construction
Manager, and Job Order Contracting when they meet certain statutory requirements. The
Capital Projects Advisory Review Board (CPARB) actively engages stakeholders to make
improvements to contracting methods and recommends policy changes to the Legislature.
The Project Review Committee (PRC) employs a consistent process to evaluate
applications for certification and project approval to ensure that applicants meet
statutory requirements.
2. Does the alternative process provide for efficient and economical public works
construction, with adequate cost controls in place?
Yes. Stakeholders report that alternative contracting methods enable
development teams to identify and assess risks earlier in the project and mitigate
those risks more effectively. Inclusion of the contractor during the design phase can
also allow for value engineering and more efficient scheduling, which can save on
overall costs or provide greater value. Projects tend to have greater cost certainty,
and overall cost includes a contingency to cover unanticipated adjustments during
construction. Expenditures in the 2017-19 biennium were $281,330 to support CPARB.
3. Has CPARB achieved expected performance measures?
Yes. CPARB has achieved the performance measures it established for itself.
The measures address CPARB’s statutory authority and the Sunset questions. For
example, CPARB recommended policy changes and submitted requested reports to the
Legislature.
4. What would be the effect of termination?
Stakeholders we interviewed oppose termination. When asked about the impact of
terminating the alternative public works statute, stakeholders reported that it would
likely lead to more disputes, more lawsuits, more change orders, more design and
construction uncertainty, greater risk exposure, slower construction, and more
expensive or lower quality projects. Interviewed firms that specialize in alternative
delivery methods said they would likely give up public work in favor of private sector
projects if the alternative contracting methods were terminated.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Report Details
Appendix A: Certified public bodies and approved projects
The Project Review Committee reviews applications from public
bodies to use Design-Build or General Contractor/Construction Manager contracting
methods
At the time of our review, there were 13 public bodies certified to use Design-Build
and/or General Contractor/Construction Manager (GC/CM) contracting methods. Between
2013 and June 2020, the Project Review Committee (PRC) approved 179 projects.
Certified Public Bodies
Public bodies can apply for agency certification that allows them to choose between
alternative and traditional contracting methods through their own decision making
processes. Certification lasts for three years.
Exhibit A1: Certified Public Bodies as of August 2020
Click header to sort.
Certified Public Owners
Alternative Method
Central Valley School District
GC/CM
City of Seattle
Design-Build and GC/CM
City of Tacoma
Design-Build
Clover Park School District
GC/CM
Dept. Enterprise Services
Design-Build and GC/CM
Edmonds School District
GC/CM
Lake Washington School District
GC/CM
Mason General Hospital
GC/CM
Port of Seattle
Design-Build and GC/CM
Sound Transit
Design-Build and GC/CM
Spokane Public Schools
GC/CM
University of Washington
Design-Build and GC/CM
Washington State University
Design-Build and GC/CM
Source: PRC list of active certifications.
Certification and recertification applications include limited information about
projects completed, underway, or planned to enable PRC members to assess the public
body's expertise with alternative contracting methods. JLARC staff extracted 163
projects that had both date and cost information to demonstrate use of the contracting
methods (see Exhibit A2). Projects without sufficient information were not
included.
Project approvals
Between 2013 and June of 2020, the PRC approved 179 design-build or GC/CM project
applications submitted by 96 public bodies. 43 of the public bodies were school
districts (accounted for 92 of the projects), 16 were cities (29 projects), and 9 were
hospital districts (10 projects). The list of projects is available in Exhibit A2.
Design-Build and GC/CM projects approved by or reported to the PRC between 2013 and
June 2020
Exhibit A2: Design-build and GC/CM projects approved or reported between 2013 and
June 2020
Source: Applications to the PRC for certification, recertification, or project
approval. Data includes projects approved, begun, or completed between 2013 and June
2020. For projects reported by certified public bodies, date information includes
actual or planned completion dates.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
39.10.320 Design-build procedure—Project management and contracting requirements.
39.10.330 Design-build contract award process.
39.10.340 General contractor/construction manager procedure—Uses.
39.10.350 General contractor/construction manager procedure—Project management and
contracting requirements.
39.10.360 General contractor/construction manager procedure—Contract award process.
39.10.370 General contractor/construction manager procedure—Maximum allowable
construction cost.
39.10.380 General contractor/construction manager procedure—Subcontract bidding
procedure.
39.10.385 General contractor/construction manager procedure—Alternative subcontractor
selection process.
39.10.390 General contractor/construction manager procedure—Subcontract work.
39.10.400 General contractor/construction manager procedure—Prebid determination of
subcontractor eligibility.
39.10.410 General contractor/construction manager procedure—Subcontract agreements.
39.10.420 Job order procedure—Public bodies may authorize and use.
39.10.430 Job order procedure—Contract award process.
39.10.440 Job order procedure—Contract requirements.
39.10.450 Job order procedure—Work orders.
39.10.460 Job order procedure—Required information to board.
39.10.470 Public inspection of certain records—Protection of trade secrets—Protection
of documents submitted.
39.10.480 Construction of chapter—Waiver of other limits and requirements.
39.10.490 Application of chapter.
39.10.900 Captions not law—1994 c 132.
39.10.901 Severability—1994 c 132.
39.10.903 Part headings and captions not law—2007 c 494.
39.10.904 Effective dates—2007 c 494. 39.10.905 Severability—2007 c 494.
NOTES: Reviser's note—Sunset Act application: The alternative public works
contracting procedures are subject to review, termination, and possible extension
under chapter 43.131 RCW, the Sunset Act. See RCW 43.131.407. RCW 39.10.200 through
39.10.905 are scheduled for future repeal under RCW 43.131.408.
RCW 39.10.200
Finding—Purpose—Intent.
The legislature finds that the traditional process of awarding public works contracts
in lump sum to the lowest responsible bidder is a fair and objective method of
selecting a contractor. However, under certain circumstances, alternative public works
contracting procedures may best serve the public interest if such procedures are
implemented in an open and fair process based on objective and equitable criteria. The
purpose of this chapter is to authorize the use of certain supplemental alternative
public works contracting procedures, to prescribe appropriate requirements to ensure
that such contracting procedures serve the public interest, and to establish a process
for evaluation of such contracting procedures. It is the intent of the legislature to
establish that, unless otherwise specifically provided for in law, public bodies may
use only those alternative public works contracting procedures specifically authorized
in this chapter, subject to the requirements of this chapter. [ 2010 1st sp.s. c 21 §
2; 2007 c 494 § 1; 1994 c 132 § 1. Formerly RCW 39.10.010.]
NOTES: Sunset Act application: See note following chapter digest. Intent—2010 1st
sp.s. c 21: "The establishment of alternative public works contracting procedures
authorized for use by public bodies has been a complex, controversial, and challenging
undertaking, but it has been successful. The key to the successful adoption and
consideration of these procedures has depended, in great part, on the review and
oversight mechanisms put in place by the legislature in chapter 39.10 RCW, as well as
the countless hours of dedicated work by numerous stakeholders over many years. It is
the intent of the legislature to clarify that, unless otherwise specifically provided
for in law, public bodies that want to use an alternative public works contracting
procedure may use only those procedures specifically authorized in chapter 39.10 RCW."
[ 2010 1st sp.s. c 21 § 1.]
RCW 39.10.210
Definitions.
Unless the context clearly requires otherwise, the definitions in this section apply
throughout this chapter.
(1) "Alternative public works contracting procedure" means the design-build, general
contractor/construction manager, and job order contracting procedures authorized in
RCW 39.10.300, 39.10.340, and 39.10.420, respectively.
(2) "Board" means the capital projects advisory review board.
(3) "Certified public body" means a public body certified to use design-build or
general contractor/construction manager contracting procedures, or both, under RCW
39.10.270.
(4) "Committee," unless otherwise noted, means the project review committee.
(5) "Design-build procedure" means a contract between a public body and another party
in which the party agrees to both design and build the facility, portion of the
facility, or other item specified in the contract.
(6) "Disadvantaged business enterprise" means any business entity certified with the
office of minority and women's business enterprises under chapter 39.19 RCW.
(7) "General contractor/construction manager" means a firm with which a public body
has selected to provide services during the design phase and negotiated a maximum
allowable construction cost to act as construction manager and general contractor
during the construction phase.
(8) "Heavy civil construction project" means a civil engineering project, the
predominant features of which are infrastructure improvements.
(9) "Job order contract" means a contract in which the contractor agrees to a fixed
period, indefinite quantity delivery order contract which provides for the use of
negotiated, definitive work orders for public works as defined in RCW 39.04.010.
(10) "Job order contractor" means a registered or licensed contractor awarded a job
order contract.
(11) "Maximum allowable construction cost" means the maximum cost of the work to
construct the project including a percentage for risk contingency, negotiated support
services, and approved change orders.
(12) "Negotiated support services" means items a general contractor would normally
manage or perform on a construction project including, but not limited to surveying,
hoisting, safety enforcement, provision of toilet facilities, temporary heat, cleanup,
and trash removal, and that are negotiated as part of the maximum allowable
construction cost.
(13) "Percent fee" means the percentage amount to be earned by the general
contractor/construction manager as overhead and profit.
(14) "Price-related factor" means an evaluation factor that impacts costs which may
include, but is not limited to overhead and profit, lump sum or guaranteed maximum
price for the entire or a portion of the project, operating costs, or other similar
factors that may apply to the project.
(15) "Public body" means any general or special purpose government in the state of
Washington, including but not limited to state agencies, institutions of higher
education, counties, cities, towns, ports, school districts, and special purpose
districts.
(16) "Public works project" means any work for a public body within the definition of
"public work" in RCW 39.04.010.
(17) "Small business entity" means a small business as defined in RCW 39.26.010.
(18) "Total contract cost" means the fixed amount for the detailed specified general
conditions work, the negotiated maximum allowable construction cost, and the percent
fee on the negotiated maximum allowable construction cost.
(19) "Total project cost" means the cost of the project less financing and land
acquisition costs.
(20) "Unit price book" means a book containing specific prices, based on generally
accepted industry standards and information, where available, for various items of
work to be performed by the job order contractor. The prices may include: All the
costs of materials; labor; equipment; overhead, including bonding costs; and profit
for performing the items of work. The unit prices for labor must be at the rates in
effect at the time the individual work order is issued.
(21) "Work order" means an order issued for a definite scope of work to be performed
pursuant to a job order contract.
[ 2019 c 212 § 1. Prior: 2014 c 42 § 1; 2013 c 222 § 1; prior: 2010 1st sp.s. c 36 §
6014; 2007 c 494 § 101; 2005 c 469 § 3; prior: 2003 c 352 § 1; 2003 c 301 § 2; 2003 c
300 § 3; 2001 c 328 § 1; 2000 c 209 § 1; 1997 c 376 § 1; 1994 c 132 § 2. Formerly RCW
39.10.020.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: "Sections 1 through 23 of this act are necessary for the
immediate preservation of the public peace, health, or safety, or support of the state
government and its existing public institutions, and take effect June 30, 2013." [
2013 c 222 § 26.]
Effective date—2010 1st sp.s. c 36: See note following RCW 43.155.050.
Effective date—2001 c 328: "This act is necessary for the immediate preservation of
the public peace, health, or safety, or support of the state government and its
existing public institutions, and takes effect July 1, 2001." [ 2001 c 328 § 8.]
Effective date—1997 c 376: "This act is necessary for the immediate preservation of
the public peace, health, or safety, or support of the state government and its
existing public institutions, and takes effect July 1, 1997." [ 1997 c 376 § 10.]
RCW 39.10.220
Board—Membership—Vacancies.
(1) The board is created in the department of enterprise services to provide an
evaluation of public capital projects construction processes, including the impact of
contracting methods on project outcomes, and to advise the legislature on policies
related to public works delivery methods.
(2) Members of the board are appointed as follows:
(a) Two representatives from construction general contracting; one representative
from the architectural profession; one representative from the engineering profession;
two representatives from construction specialty subcontracting; two representatives
from construction trades labor organizations; one representative from the office of
minority and women's business enterprises; one representative from a higher education
institution; one representative from the department of enterprise services; one
individual representing Washington cities; two representatives from private industry;
and one representative of a domestic insurer authorized to write surety bonds for
contractors in Washington state, each appointed by the governor. All appointed members
must be knowledgeable about public works contracting procedures. If a vacancy occurs,
the governor shall fill the vacancy for the unexpired term;
(b) One member representing counties, selected by the Washington state association of
counties;
(c) One member representing public ports, selected by the Washington public ports
association;
(d) One member representing public hospital districts, selected by the association of
Washington public hospital districts;
(e) One member representing school districts, selected by the Washington state school
directors' association; and
(f) Two members of the house of representatives, one from each major caucus,
appointed by the speaker of the house of representatives, and two members of the
senate, one from each major caucus, appointed by the president of the senate.
Legislative members are nonvoting.
(3) Members selected under subsection (2)(a) of this section shall serve for terms of
four years, with the terms expiring on June 30th on the fourth year of the term.
(4) The board chair is selected from among the appointed members by the majority vote
of the voting members.
(5) Legislative members of the board shall be reimbursed for travel expenses in
accordance with RCW 44.04.120. Nonlegislative members of the board, project review
committee members, and committee chairs shall be reimbursed for travel expenses as
provided in RCW 43.03.050 and 43.03.060.
(6) Vacancies are filled in the same manner as appointed. Members of the board may be
removed for malfeasance or misfeasance in office, upon specific written charges by the
governor, under chapter 34.05 RCW.
(7) The board shall meet as often as necessary.
(8) Board members are expected to consistently attend board meetings. The chair of
the board may ask the governor to remove any member who misses more than two meetings
in any calendar year without cause.
(9) The department of enterprise services shall provide staff support as may be
required for the proper discharge of the function of the board.
(10) The board may establish committees as it desires and may invite nonmembers of
the board to serve as committee members.
(11) The board shall encourage participation from persons and entities not
represented on the board.
[ 2013 c 222 § 2; 2007 c 494 § 102; 2005 c 377 § 1. Formerly RCW 39.10.800.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.230
Board—Powers and duties.
The board has the following powers and duties:
(1) Develop and recommend to the legislature policies to further enhance the quality,
efficiency, and accountability of capital construction projects through the use of
traditional and alternative delivery methods in Washington, and make recommendations
regarding expansion, continuation, elimination, or modification of the alternative
public works contracting methods;
(2) Evaluate the use of existing contracting procedures and the potential future use
of other alternative contracting procedures including competitive negotiation
contracts;
(3) Submit recommendations to the appropriate committees of the legislature
evaluating alternative contracting procedures that are not authorized under this
chapter;
(4) Appoint members of committees; and
(5) Develop and administer questionnaires designed to provide quantitative and
qualitative data on alternative public works contracting procedures on which
evaluations are based.
The capital projects advisory review board is directed to review current statutes
regarding life-cycle cost analysis and energy efficiency as related to the
design-build procurement method performed under chapter 39.10 RCW. Capital projects
advisory review board shall report to the appropriate committees of the legislature by
December 31, 2013, with recommendations for statutory changes that promote energy
efficiency and reduce the total cost to construct, operate and maintain public
buildings. Recommendation must include provisions for postoccupancy validation of
estimated energy efficiency measures, and operating and maintenance cost estimates.
Life-cycle estimates of energy use must include estimates of energy consumptions for
materials used in construction.
[ 2013 c 222 § 3; 2010 1st sp.s. c 21 § 3; 2009 c 75 § 1; 2007 c 494 § 103; 2005 c
377 § 2. Formerly RCW 39.10.810.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
Intent—2010 1st sp.s. c 21: See note following RCW 39.10.200.
RCW 39.10.240
Project review committee—Creation—Members.
(1) The board shall establish a project review committee to review and approve public
works projects using the design-build and general contractor/construction manager
contracting procedures authorized in RCW 39.10.300 and 39.10.340 and to certify public
bodies as provided in RCW 39.10.270.
(2) The board shall, by a majority vote of the board, appoint persons to the
committee who are knowledgeable in the use of the design-build and general
contractor/construction manager contracting procedures. Appointments must represent a
balance among the industries and public owners on the board listed in RCW 39.10.220.
(a) Each member of the committee shall be appointed for a term of three years.
However, for initial appointments, the board shall stagger the appointment of
committee members so that the first members are appointed to serve terms of one, two,
or three years from the date of appointment. Appointees may be reappointed to serve
more than one term.
(b) The committee shall, by a majority vote, elect a chair and vice chair for the
committee.
(c) The committee chair may select a person or persons on a temporary basis as a
nonvoting member if project specific expertise is needed to assist in a review.
(3) The chair of the committee, in consultation with the vice chair, may appoint one
or more panels of at least six committee members to carry out the duties of the
committee. Each panel shall have balanced representation of the private and public
sector representatives serving on the committee.
(4) Any member of the committee directly or indirectly affiliated with a submittal
before the committee must recuse himself or herself from the committee consideration
of that submittal.
(5) Any person who sits on the committee or panel is not precluded from subsequently
bidding on or participating in projects that have been reviewed by the committee.
(6) The committee shall meet as often as necessary to ensure that certification and
approvals are completed in a timely manner.
[ 2013 c 222 § 4; 2007 c 494 § 104.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.250
Project review committee—Duties.
The committee shall:
(1) Certify, or renew certification for, public bodies to use design-build or general
contractor/construction manager contracting procedures, or both;
(2) Review and approve the use of the design-build or general contractor/construction
manager contracting procedures on a project by project basis for public bodies that
are not certified under RCW 39.10.270;
(3) Review and approve not more than two design-build demonstration projects that
include procurement of operations and maintenance services for a period longer than
three years.
[ 2019 c 212 § 2; 2013 c 222 § 5; 2009 c 75 § 2; 2007 c 494 § 105.]
NOTES: Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.260
Project review committee—Meetings—Open and public.
(1) The committee shall hold regular public meetings to carry out its duties as
described in RCW 39.10.250. Committee meetings are subject to chapter 42.30 RCW.
(2) The committee shall publish notice of its public meetings at least twenty days
before the meeting in a legal newspaper circulated in the area where the public body
seeking certification is located, or where each of the proposed projects under
consideration will be constructed. All meeting notices must be posted on the
committee's web site.
(3) The meeting notice must identify the public body that is seeking certification or
project approval, and where applicable, a description of projects to be considered at
the meeting. The notice must indicate when, where, and how the public may present
comments regarding the committee's certification of a public body or approval of a
project. Information submitted by a public body to be reviewed at the meeting shall be
available on the committee's web site at the time the notice is published.
(4) The committee must allow for public comment on the appropriateness of
certification of a public body or on the appropriateness of the use of the proposed
contracting procedure and the qualifications of a public body to use the contracting
procedure. The committee shall receive and record both written and oral comments at
the public meeting.
[ 2013 c 222 § 6; 2007 c 494 § 106.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.270
Project review committee—Certification of public bodies.
(1) A public body may apply for certification to use the design-build or general
contractor/construction manager contracting procedure, or both. Once certified, a
public body may use the contracting procedure for which it is certified on individual
projects without seeking committee approval for a period of three years. A public body
seeking certification must submit to the committee an application in a format and
manner as prescribed by the committee. The application must include a description of
the public body's qualifications, its capital plan during the certification period,
and its intended use of alternative contracting procedures.
(2) A public body seeking certification for the design-build procedure must
demonstrate successful management of at least one design-build project within the
previous five years. A public body seeking certification for the general
contractor/construction manager procedure must demonstrate successful management of at
least one general contractor/construction manager project within the previous five
years.
(3) To certify a public body, the committee shall determine that the public body:
(a) Has the necessary experience and qualifications to determine which projects are
appropriate for using alternative contracting procedures;
(b) Has the necessary experience and qualifications to carry out the alternative
contracting procedure including, but not limited to:
(i) Project delivery knowledge and experience;
(ii) personnel with appropriate construction experience;
(iii) a management plan and rationale for its alternative public works projects;
(iv) demonstrated success in managing public works projects;
(v) the ability to properly manage its capital facilities plan including, but not
limited to, appropriate project planning and budgeting experience; and
(vi) the ability to meet requirements of this chapter; and
(c) Has resolved any audit findings on previous public works projects in a manner
satisfactory to the committee.
(4) The committee shall make its determination at the public meeting during which an
application for certification is reviewed. Public comments must be considered before a
determination is made. Within ten business days of the public meeting, the committee
shall provide a written determination to the public body, and make its determination
available to the public on the committee's web site.
(5) The committee may revoke any public body's certification upon a finding, after a
public hearing, that its use of design-build or general contractor/construction
manager contracting procedures no longer serves the public interest.
(6) The committee may renew the certification of a public body for additional
three-year periods. The public body must submit an application for recertification at
least three months before the initial certification expires. The committee may accept
late applications, if administratively feasible, to avoid expiration of certification
on a case-by-case basis. The application shall include updated information on the
public body's experience and current staffing with the procedure it is applying to
renew, and any other information requested in advance by the committee. The committee
must review the application for recertification at a meeting held before expiration of
the applicant's initial certification period. A public body must reapply for
certification under the process described in subsection (1) of this section once the
period of recertification expires.
(7) Certified public bodies must submit project data information as required in RCW
39.10.320 and 39.10.350.
[ 2019 c 212 § 3; 2017 c 211 § 1; 2013 c 222 § 7; 2009 c 75 § 3; 2007 c 494 § 107.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
(1) A public body not certified under RCW 39.10.270 must apply for approval from the
committee to use the design-build or general contractor/construction manager
contracting procedure on a project. A public body seeking approval must submit to the
committee an application in a format and manner as prescribed by the committee. The
application must include a description of the public body's qualifications, a
description of the project, the public body's intended use of alternative contracting
procedures, and, if applicable, a declaration that the public body has elected to
procure the project as a heavy civil construction project.
(2) To approve a proposed project, the committee shall determine that:
(a) The alternative contracting procedure will provide a substantial fiscal benefit
or the use of the traditional method of awarding contracts in lump sum to the low
responsive bidder is not practical for meeting desired quality standards or delivery
schedules;
(b) The proposed project meets the requirements for using the alternative contracting
procedure as described in RCW 39.10.300 or 39.10.340;
(c) The public body has the necessary experience or qualified team to carry out the
alternative contracting procedure including, but not limited to: (i) Project delivery
knowledge and experience; (ii) sufficient personnel with construction experience to
administer the contract; (iii) a written management plan that shows clear and logical
lines of authority; (iv) the necessary and appropriate funding and time to properly
manage the job and complete the project; (v) continuity of project management team,
including personnel with experience managing projects of similar scope and size to the
project being proposed; and (vi) necessary and appropriate construction budget;
(d) For design-build projects, public body personnel or consultants are knowledgeable
in the design-build process and are able to oversee and administer the contract; and
(e) The public body has resolved any audit findings related to previous public works
projects in a manner satisfactory to the committee.
(3) The committee shall, if practicable, make its determination at the public meeting
during which a submittal is reviewed. Public comments must be considered before a
determination is made. (4) Within ten business days after the public meeting, the
committee shall provide a written determination to the public body, and make its
determination available to the public on the committee's web site. If the committee
fails to make a written determination within ten business days of the public meeting,
the request of the public body to use the alternative contracting procedure on the
requested project shall be deemed approved. (5) Failure of the committee to meet
within sixty calendar days of a public body's application to use an alternative
contracting procedure on a project shall be deemed an approval of the application.
[ 2014 c 42 § 2; 2013 c 222 § 8; 2007 c 494 § 108.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.290
Appeal process.
Final determinations by the committee may be appealed to the board within seven days
by the public body or by an interested party. A written notice of an appeal must be
provided to the committee and, as applicable, to the public body. The board shall
resolve an appeal within forty-five days of receipt of the appeal and shall send a
written determination of its decision to the party making the appeal and to the
appropriate public body, as applicable. The public body shall comply with the
determination of the board.
[ 2007 c 494 § 109.]
NOTES: Sunset Act application: See note following chapter digest.
RCW 39.10.300
Design-build procedure—Uses.
(1) Subject to the requirements in RCW 39.10.250, 39.10.270, or 39.10.280, public
bodies may utilize the design-build procedure, including progressive design-build, for
public works projects in which the total project cost is over two million dollars and
where:
(a) The construction activities are highly specialized and a design-build approach is
critical in developing the construction methodology; or
(b) The projects selected provide opportunity for greater innovation or efficiencies
between the designer and the builder; or
(c) Significant savings in project delivery time would be realized.
(2) Subject to the process in RCW 39.10.270 or 39.10.280, public bodies may use the
design-build procedure for parking garages, regardless of cost.
(3) The design-build procedure may be used for the construction or erection of
portable facilities as defined in WAC 392-343-018, preengineered metal buildings, or
not more than ten prefabricated modular buildings per installation site, regardless of
cost and is not subject to approval by the committee.
(4) Except for utility projects and approved demonstration projects, the design-build
procedure may not be used to procure operations and maintenance services for a period
longer than three years. State agency projects that propose to use the
design-build-operate-maintain procedure shall submit cost estimates for the
construction portion of the project consistent with the office of financial
management's capital budget requirements. Operations and maintenance costs must be
shown separately and must not be included as part of the capital budget request.
(5) Subject to the process in RCW 39.10.280, a public body may seek committee
approval for a design-build demonstration project that includes procurement of
operations and maintenance services for a period longer than three years.
[ 2019 c 212 § 4; 2013 c 222 § 9; 2009 c 75 § 4; 2007 c 494 § 201. Prior: 2003 c 352
§ 2; 2003 c 300 § 4; 2002 c 46 § 1; 2001 c 328 § 2. Formerly RCW 39.10.051.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
Effective date—2002 c 46: "This act is necessary for the immediate preservation of
the public peace, health, or safety, or support of the state government and its
existing public institutions, and takes effect immediately [March 14, 2002]." [ 2002 c
46 § 5.]
Effective date—2001 c 328: See note following RCW 39.10.210.
RCW 39.10.320
Design-build procedure—Project management and contracting requirements.
(1) A public body utilizing the design-build contracting procedure shall provide:
(a) Reasonable budget contingencies totaling not less than five percent of the
anticipated contract value;
(b) Staff or consultants with expertise and prior experience in the management of
comparable projects;
(c) Contract documents that include alternative dispute resolution procedures to be
attempted prior to the initiation of litigation;
(d) Submission of project information, as required by the board;
(e) Contract documents that require the contractor, subcontractors, and designers to
submit project information required by the board; and
(f) Contract documents that require the design builder to submit plans for inclusion
of underutilized firms as subcontractors and suppliers including, but not limited to,
the office of minority and women's business enterprises certified businesses, veteran
certified businesses, and small businesses as allowed by law.
(2) A public body utilizing the design-build contracting procedure may provide
incentive payments to contractors for early completion, cost savings, or other goals
if such payments are identified in the request for proposals.
[ 2019 c 212 § 5; 2013 c 222 § 10; 2007 c 494 § 203; 1994 c 132 § 7. Formerly RCW
39.10.070.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.330
Design-build contract award process.
(1) Contracts for design-build services shall be awarded through a competitive
process using public solicitation of proposals for design-build services. The public
body shall publish at least once in a legal newspaper of general circulation published
in, or as near as possible to, that part of the county in which the public work will
be done, a notice of its request for qualifications from proposers for design-build
services, and the availability and location of the request for proposal documents. The
request for qualifications documents shall include:
(a) A description of the project including the estimated design-build contract value
and the intended use of the project;
(b) The reasons for using the design-build procedure;
(c) A description of the qualifications to be required of the proposer;
(d) A description of the process the public body will use to evaluate qualifications
and finalists' proposals, including evaluation factors and the relative weight of
factors and any specific forms to be used by the proposers;
(i) Evaluation factors for qualifications shall include technical qualifications,
such as specialized experience and technical competence of the firms and the key
design and construction personnel; capacity to perform; the proposer's past
performance in utilization of the office of minority and women's business enterprises
certified businesses, to the extent permitted by law; ability to provide a performance
and payment bond for the project; and other appropriate factors. Evaluation factors
may also include, but are not limited to, the proposer's past performance in
utilization of small business entities. Cost or price-related factors are not
permitted in the request for qualifications phase;
(ii) Evaluation factors for finalists' proposals shall include the management plan to
meet time and budget requirements and one or more price-related factors. Evaluation
factors may also include, but not be limited to, the technical approach, design
concept, and the outreach plan to include small business entities and disadvantaged
business enterprises as subconsultants, subcontractors, and suppliers for the project;
(e) Protest procedures including time limits for filing a protest, which in no event
may limit the time to file a protest to fewer than four business days from the date
the proposer was notified of the selection decision;
(f) The proposed contract;
(g) The honorarium to be paid to finalists submitting responsive proposals and who
are not awarded a design-build contract;
(h) The schedule for the procurement process and the project; and
(i) Other information relevant to the project.
(2) The public body shall establish an evaluation committee to evaluate the responses
to the request for qualifications based solely on the factors, weighting, and process
identified in the request for qualifications and any addenda issued by the public
body. Based on the evaluation committee's findings, the public body shall select not
more than five responsive and responsible finalists to submit proposals. The public
body may, in its sole discretion, reject all proposals and shall provide its reasons
for rejection in writing to all proposers.
(3) The public body must notify all proposers of the finalists selected to move to
the next phase of the selection process. The process may not proceed to the next phase
until two business days after all proposers are notified of the committee's selection
decision. At the request of a proposer not selected as a finalist, the public body
must provide the requesting proposer with a scoring summary of the evaluation factors
for its proposal. Proposers filing a protest on the selection of the finalists must
file the protest in accordance with the published protest procedures. The selection
process may not advance to the next phase of selection until two business days after
the final protest decision is transmitted to the protestor.
(4) Upon selection of the finalists, the public body shall issue a request for
proposals to the finalists. The request for proposal documents shall include:
(a) Any specific forms to be used by the finalists; and
(b) Submission of a summary of the finalist's accident prevention program and an
overview of its implementation.
(5) The public body shall establish an evaluation committee to evaluate the proposals
submitted by the finalists. The finalists' proposals shall be evaluated and scored
based solely on the factors, weighting, and process identified in the request for
qualifications, the request for proposals, and in any addenda published by the public
body. Public bodies may request best and final proposals from finalists. The public
body may initiate negotiations with the finalist submitting the highest scored
proposal. If the public body is unable to execute a contract with the finalist
submitting the highest scored proposal, negotiations with that finalist may be
suspended or terminated and the public body may proceed to negotiate with the next
highest scored finalist. Public bodies shall continue in accordance with this
procedure until a contract agreement is reached or the selection process is
terminated.
(6) The public body shall notify all finalists of the selection decision and make a
selection summary of the final proposals available to all proposers within two
business days of such notification. If the public body receives a timely written
protest from a finalist firm, the public body may not execute a contract until two
business days after the final protest decision is transmitted to the protestor. The
protestor must submit its protest in accordance with the published protest procedures.
(7) The firm awarded the contract shall provide a performance and payment bond for
the contracted amount.
(8) Any contract must require the firm awarded the contract to track and report to
the public body its utilization of the office of minority and women's business
enterprises certified businesses and veteran certified businesses.
(9) The public body shall provide appropriate honorarium payments to finalists
submitting responsive proposals that are not awarded a design-build contract.
Honorarium payments shall be sufficient to generate meaningful competition among
potential proposers on design-build projects. In determining the amount of the
honorarium, the public body shall recognize the level of effort required to meet the
selection criteria.
[ 2019 c 212 § 6; 2014 c 19 § 1; 2013 c 222 § 11; 2009 c 75 § 5; 2007 c 494 § 204.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.340
General contractor/construction manager procedure—Uses.
Subject to the process in RCW 39.10.270 or 39.10.280, public bodies may utilize the
general contractor/construction manager procedure for public works projects where at
least one of the following is met:
(1) Implementation of the project involves complex scheduling, phasing, or
coordination;
(2) The project involves construction at an occupied facility which must continue to
operate during construction;
(3) The involvement of the general contractor/construction manager during the design
stage is critical to the success of the project;
(4) The project encompasses a complex or technical work environment;
(5) The project requires specialized work on a building that has historic
significance; or
(6) The project is, and the public body elects to procure the project as, a heavy
civil construction project. However, no provision of this chapter pertaining to a
heavy civil construction project applies unless the public body expressly elects to
procure the project as a heavy civil construction project.
[ 2014 c 42 § 3; 2013 c 222 § 12; 2007 c 494 § 301. Prior: 2003 c 352 § 3; 2003 c 300
§ 5; 2002 c 46 § 2; 2001 c 328 § 3. Formerly RCW 39.10.061.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
Effective date—2002 c 46: See note following RCW 39.10.300.
Effective date—2001 c 328: See note following RCW 39.10.210.
RCW 39.10.350
General contractor/construction manager procedure—Project management and contracting
requirements.
(1) A public body using the general contractor/construction manager contracting
procedure shall provide for:
(a) The preparation of appropriate, complete, and coordinated design documents;
(b) Confirmation that a constructability analysis of the design documents has been
performed prior to solicitation of a subcontract bid package;
(c) Reasonable budget contingencies totaling not less than five percent of the
anticipated contract value;
(d) To the extent appropriate, on-site architectural or engineering representatives
during major construction or installation phases;
(e) Employment of staff or consultants with expertise and prior experience in the
management of comparable projects, critical path method schedule review and analysis,
and the administration, pricing, and negotiation of change orders;
(f) Contract documents that include alternative dispute resolution procedures to be
attempted before the initiation of litigation;
(g) Contract documents that:
(i) Obligate the public owner to accept or reject a request for equitable adjustment,
change order, or claim within a specified time period but no later than sixty calendar
days after the receipt by the public body of related documentation; and
(ii) provide that if the public owner does not respond in writing to a request for
equitable adjustment, change order, or claim within the specified time period, the
request is deemed denied;
(h) Submission of project information, as required by the board; and
(i) Contract documents that require the contractor, subcontractors, and designers to
submit project information required by the board.
(2) A public body using the general contractor/construction manager contracting
procedure may include an incentive clause for early completion, cost savings, or other
performance goals if such incentives are identified in the request for proposals. No
incentives granted may exceed five percent of the maximum allowable construction cost.
No incentives may be paid from any contingency fund established for coordination of
the construction documents or coordination of the work.
(3) If the construction is completed for less than the maximum allowable construction
cost, any savings not otherwise negotiated as part of an incentive clause shall accrue
to the public body. If the construction is completed for more than the maximum
allowable construction cost, the additional cost is the responsibility of the general
contractor/construction manager.
(4) If the public body and the general contractor/construction manager agree, in
writing, on a price for additional work, the public body must issue a change order
within thirty days of the written agreement. If the public body does not issue a
change order within the thirty days, interest shall accrue on the dollar amount of the
additional work satisfactorily completed until a change order is issued. The public
body shall pay this interest at a rate of one percent per month.
(5) For a project procured as a heavy civil construction project, an independent
audit, paid for by the public body, must be conducted to confirm the proper accrual of
costs as outlined in the contract.
[ 2014 c 42 § 4; 2007 c 494 § 302.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.360
General contractor/construction manager procedure—Contract award process.
(1) Public bodies should select general contractor/construction managers early in the
life of public works projects, and in most situations no later than the completion of
schematic design.
(2) Contracts for the services of a general contractor/ construction manager under
this section shall be awarded through a competitive process requiring the public
solicitation of proposals for general contractor/construction manager services. The
public solicitation of proposals shall include:
(a) A description of the project, including programmatic, performance, and technical
requirements and specifications when available;
(b) The reasons for using the general contractor/construction manager procedure
including, if applicable, a clear statement that the public body is electing to
procure the project as a heavy civil construction project, in which case the
solicitation must additionally:
(i) Indicate the minimum percentage of the cost of the work to construct the project
that will constitute the negotiated self-perform portion of the project;
(ii) Indicate whether the public body will allow the price to be paid for the
negotiated self-perform portion of the project to be deemed a cost of the work to
which the general contractor/construction manager's percent fee applies; and
(iii) Require proposals to indicate the proposer's fee for the negotiated
self-perform portion of the project;
(c) A description of the qualifications to be required of the firm, including
submission of the firm's accident prevention program;
(d) A description of the process the public body will use to evaluate qualifications
and proposals, including evaluation factors, the relative weight of factors, and
protest procedures including time limits for filing a protest, which in no event may
limit the time to file a protest to fewer than four business days from the date the
proposer was notified of the selection decision;
(e) The form of the contract, including any contract for preconstruction services, to
be awarded;
(f) The estimated maximum allowable construction cost; and
(g) The bid instructions to be used by the general contractor/construction manager
finalists.
(3)(a) Evaluation factors for selection of the general contractor/construction
manager shall include, but not be limited to:
(i) Ability of the firm's professional personnel;
(ii) The firm's past performance in negotiated and complex projects;
(iii) The firm's ability to meet time and budget requirements;
(iv) The scope of work the firm proposes to self-perform and its ability to perform
that work;
(v) The firm's proximity to the project location;
(vi) Recent, current, and projected workloads of the firm; and
(vii) The firm's approach to executing the project.
(b) An agency may also consider the firm's outreach plan to include small business
entities and disadvantaged business enterprises, and the firm's past performance in
the utilization of such firms as an evaluation factor.
(4) A public body shall establish a committee to evaluate the proposals. After the
committee has selected the most qualified finalists, at the time specified by the
public body, these finalists shall submit final proposals, including sealed bids for
the percent fee on the estimated maximum allowable construction cost and the fixed
amount for the general conditions work specified in the request for proposal. The
public body shall establish a time and place for the opening of sealed bids for the
percent fee on the estimated maximum allowable construction cost and the fixed amount
for the general conditions work specified in the request for proposal. At the time and
place named, these bids must be publicly opened and read and the public body shall
make all previous scoring available to the public. The public body shall select the
firm submitting the highest scored final proposal using the evaluation factors and the
relative weight of factors published in the public solicitation of proposals. A public
body shall not evaluate or disqualify a proposal based on the terms of a collective
bargaining agreement.
(5) The public body shall notify all finalists of the selection decision and make a
selection summary of the final proposals available to all proposers within two
business days of such notification. If the public body receives a timely written
protest from a proposer, the public body may not execute a contract until two business
days after the final protest decision is transmitted to the protestor. The protestor
must submit its protest in accordance with the published protest procedures.
(6) Public bodies may contract with the selected firm to provide services during the
design phase that may include life-cycle cost design considerations, value
engineering, scheduling, cost estimating, constructability, alternative construction
options for cost savings, and sequencing of work, and to act as the construction
manager and general contractor during the construction phase.
[ 2014 c 42 § 5; 2013 c 222 § 13; 2009 c 75 § 6; 2007 c 494 § 303.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.370
General contractor/construction manager procedure—Maximum allowable construction
cost.
(1) The maximum allowable construction cost shall be used to establish a total
contract cost for which the general contractor/construction manager shall provide a
performance and payment bond. The maximum allowable construction cost shall be
negotiated between the public body and the selected firm when the construction
documents and specifications are at least ninety percent complete.
(2) Major bid packages may be bid in accordance with RCW 39.10.380 before agreement
on the maximum allowable construction cost between the public body and the selected
general contractor/construction manager. The general contractor/construction manager
may issue an intent to award to the responsible bidder submitting the lowest
responsive bid.
(3) The public body may, at its option, authorize the general contractor/construction
manager to proceed with the bidding and award of bid packages and construction before
receipt of complete project plans and specifications. Any contracts awarded under this
subsection shall be incorporated in the negotiated maximum allowable construction
cost.
(4) The total contract cost includes the fixed amount for the detailed specified
general conditions work, the negotiated maximum allowable construction cost, the
negotiated support services, and the percent fee on the negotiated maximum allowable
construction cost. Negotiated support services may be included in the specified
general conditions at the discretion of the public body.
(5) If the public body is unable to negotiate a satisfactory maximum allowable
construction cost with the firm selected that the public body determines to be fair,
reasonable, and within the available funds, negotiations with that firm shall be
formally terminated and the public body shall negotiate with the next highest scored
firm and continue until an agreement is reached or the process is terminated.
(6) If the maximum allowable construction cost varies more than fifteen percent from
the bid estimated maximum allowable construction cost due to requested and approved
changes in the scope by the public body, the percent fee shall be renegotiated.
(7) As part of the negotiation of the maximum allowable construction cost under
subsection (1) of this section, on a project that the public body has elected to
procure as a heavy civil construction project:
(a) The general contractor/construction manager shall submit a proposed construction
management and contracting plan, which must include, at a minimum:
(i) The scope of work and cost estimates for each bid package;
(ii) A proposed price and scope of work for the negotiated self-perform portion of
the project;
(iii) The bases used by the general contractor/construction manager to develop all
cost estimates, including the negotiated self-perform portion of the project; and
(iv) The general contractor/construction manager's updated outreach plan to include
small business entities, disadvantaged business entities, and any other disadvantaged
or underutilized businesses as the public body may designate in the public
solicitation of proposals, as subcontractors and suppliers for the project;
(b) The public body and general contractor/construction manager may negotiate the
scopes of work to be procured by bid and the price and scope of work for the
negotiated self-perform portion of the project, if any;
(c) The negotiated self-perform portion of the project must not exceed fifty percent
of the cost of the work to construct the project;
(d) Subject to the limitation of RCW 39.10.390(4), the public body may additionally
negotiate with the general contractor/construction manager to determine on which
scopes of work the general contractor/construction manager will be permitted to bid,
if any;
(e) The public body and general contractor/construction manager shall negotiate, to
the public body's satisfaction, a fair and reasonable outreach plan;
(f) If the public body is unable to negotiate to its reasonable satisfaction a
component of this subsection (7), negotiations with the firm must be terminated and
the public body shall negotiate with the next highest scored firm and continue until
an agreement is reached or the process is terminated.
[ 2014 c 42 § 6; 2007 c 494 § 304.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.380
General contractor/construction manager procedure—Subcontract bidding procedure.
(1) All subcontract work and equipment and material purchases shall be competitively
bid with public bid openings. Subcontract bid packages and equipment and materials
purchases shall be awarded to the responsible bidder submitting the lowest responsive
bid. In preparing subcontract bid packages, the general contractor/construction
manager shall not be required to violate or waive terms of a collective bargaining
agreement.
(2) All subcontract bid packages in which bidder eligibility was not determined in
advance shall include the specific objective criteria that will be used by the general
contractor/construction manager and the public body to evaluate bidder responsibility.
If the lowest bidder submitting a responsive bid is determined by the general
contractor/construction manager and the public body not to be responsible, the general
contractor/construction manager and the public body must provide written documentation
to that bidder explaining their intent to reject the bidder as not responsible and
afford the bidder the opportunity to establish that it is a responsible bidder.
Responsibility shall be determined in accordance with criteria listed in the bid
documents. Protests concerning bidder responsibility determination by the general
contractor/construction manager and the public body shall be in accordance with
subsection (4) of this section.
(3) All subcontractors who bid work over three hundred thousand dollars shall post a
bid bond. All subcontractors who are awarded a contract over three hundred thousand
dollars shall provide a performance and payment bond for the contract amount. All
other subcontractors shall provide a performance and payment bond if required by the
general contractor/construction manager.
(4) If the general contractor/construction manager receives a written protest from a
subcontractor bidder or an equipment or material supplier, the general
contractor/construction manager shall not execute a contract for the subcontract bid
package or equipment or material purchase order with anyone other than the protesting
bidder without first providing at least two full business days' written notice to all
bidders of the intent to execute a contract for the subcontract bid package. The
protesting bidder must submit written notice of its protest no later than two full
business days following the bid opening. Intermediate Saturdays, Sundays, and legal
holidays are not counted.
(5) A low bidder who claims error and fails to enter into a contract is prohibited
from bidding on the same project if a second or subsequent call for bids is made for
the project.
(6) The general contractor/construction manager may negotiate with the lowest
responsible and responsive bidder to negotiate an adjustment to the lowest bid or
proposal price based upon agreed changes to the contract plans and specifications
under the following conditions:
(a) All responsive bids or proposal prices exceed the available funds;
(b) The apparent low responsive bid or proposal does not exceed the available funds
by the greater of one hundred twenty-five thousand dollars or two percent for projects
valued over ten million dollars; and
(c) The negotiated adjustment will bring the bid or proposal price within the amount
of available funds.
(7) If the negotiation is unsuccessful, the subcontract work or equipment or material
purchases must be rebid.
(8) The general contractor/construction manager must provide a written explanation if
all bids are rejected.
[ 2013 c 222 § 14; 2007 c 494 § 305.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.385
General contractor/construction manager procedure—Alternative subcontractor selection
process.
As an alternative to the subcontractor selection process outlined in RCW 39.10.380, a
general contractor/construction manager may, with the approval of the public body,
select mechanical subcontractors, electrical subcontractors, or both, using the
process outlined in this section. This alternative selection process may only be used
when the anticipated value of the subcontract will exceed three million dollars. When
using the alternative selection process, the general contractor/construction manager
should select the subcontractor early in the life of the public works project.
(1) In order to use this alternative selection process, the general
contractor/construction manager and the public body must determine that it is in the
best interest of the public. In making this determination the general
contractor/construction manager and the public body must:
(a) Publish a notice of intent to use this alternative selection process in a legal
newspaper published in or as near as possible to that part of the county where the
public work will be constructed. Notice must be published at least fourteen calendar
days before conducting a public hearing. The notice must include the date, time, and
location of the hearing; a statement justifying the basis and need for the alternative
selection process; how interested parties may, prior to the hearing, obtain the
evaluation criteria and applicable weight given to each criteria that will be used for
evaluation; and protest procedures including time limits for filing a protest, which
may in no event, limit the time to file a protest to fewer than four business days
from the date the proposer was notified of the selection decision;
(b) Conduct a hearing and provide an opportunity for any interested party to submit
written and verbal comments regarding the justification for using this selection
process, the evaluation criteria, weights for each criteria, and protest procedures;
(c) After the public hearing, consider the written and verbal comments received and
determine if using this alternative selection process is in the best interests of the
public; and
(d) Issue a written final determination to all interested parties. All protests of
the decision to use the alternative selection process must be in writing and submitted
to the public body within seven calendar days of the final determination. Any
modifications to the criteria, weights, and protest procedures based on comments
received during the public hearing process must be included in the final
determination.
(2) Contracts for the services of a subcontractor under this section must be awarded
through a competitive process requiring a public solicitation of proposals. Notice of
the public solicitation of proposals must be provided to the office of minority and
women's business enterprises. The public solicitation of proposals must include:
(a) A description of the project, including programmatic, performance, and technical
requirements and specifications when available;
(b) The reasons for using the alternative selection process;
(c) A description of the minimum qualifications required of the firm;
(d) A description of the process used to evaluate qualifications and proposals,
including evaluation factors and the relative weight of factors;
(e) Protest procedures;
(f) The form of the contract, including any contract for preconstruction services, to
be awarded;
(g) The estimated maximum allowable subcontract cost; and
(h) The bid instructions to be used by the finalists.
(3) Evaluation factors for selection of the subcontractor must include, but not be
limited to:
(a) Ability of the firm's professional personnel;
(b) The firm's past performance on similar projects;
(c) The firm's ability to meet time and budget requirements;
(d) The scope of work the firm proposes to perform with its own forces and its
ability to perform that work;
(e) The firm's plan for outreach to minority and women-owned businesses;
(f) The firm's proximity to the project location;
(g) The firm's capacity to successfully complete the project;
(h) The firm's approach to executing the project;
(i) The firm's approach to safety on the project;
(j) The firm's safety history; and
(k) If the firm is selected as one of the most qualified finalists, the firm's fee
and cost proposal.
(4) The general contractor/construction manager shall establish a committee to
evaluate the proposals. At least one representative from the public body shall serve
on the committee. Final proposals, including sealed bids for the percent fee on the
estimated maximum allowable subcontract cost, and the fixed amount for the subcontract
general conditions work specified in the request for proposal, will be requested from
the most qualified firms.
(5) The general contractor/construction manager must notify all proposers of the most
qualified firms that will move to the next phase of the selection process. The process
may not proceed to the next phase until two business days after all proposers are
notified of the committee's selection decision. At the request of a proposer, the
general contractor/construction manager must provide the requesting proposer with a
scoring summary of the evaluation factors for its proposal. Proposers filing a protest
on the selection of the most qualified finalists must file the protest with the public
body in accordance with the published protest procedures. The selection process may
not advance to the next phase of selection until two business days after the final
protest decision issued by the public body is transmitted to the protestor.
(6) The general contractor/construction manager and the public body shall select the
firm submitting the highest scored final proposal using the evaluation factors and the
relative weight of factors identified in the solicitation of proposals. The scoring of
the nonprice factors must be made available at the opening of the fee and cost
proposals. The general contractor/construction manager shall notify all proposers of
the selection decision and make a selection summary of the final proposals, which
shall be available to all proposers within two business days of such notification. The
general contractor/construction manager may not evaluate or disqualify a proposal
based on the terms of a collective bargaining agreement.
(7) If the public body receives a timely written protest from a "most qualified
firm," the general contractor/construction manager may not execute a contract for the
protested subcontract work until two business days after the final protest decision
issued by the public body is transmitted to the protestor. The protestor must submit
its protest in accordance with the published protest procedures.
(8) If the general contractor/construction manager is unable to negotiate a
satisfactory maximum allowable subcontract cost with the firm selected deemed by
public body and the general contractor/construction manager to be fair, reasonable,
and within the available funds, negotiations with that firm must be formally
terminated and the general contractor/construction manager may negotiate with the next
highest scored firm until an agreement is reached or the process is terminated.
(9) With the approval of the public body, the general contractor/construction manager
may contract with the selected firm to provide preconstruction services during the
design phase that may include life-cycle cost design considerations, value
engineering, scheduling, cost estimating, constructability, alternative construction
options for cost savings, and sequencing of work; and to act as the mechanical or
electrical subcontractor during the construction phase.
(10) The maximum allowable subcontract cost must be used to establish a total
subcontract cost for purposes of a performance and payment bond. Total subcontract
cost means the fixed amount for the detailed specified general conditions work, the
negotiated maximum allowable subcontract cost, and the percent fee on the negotiated
maximum allowable subcontract cost. Maximum allowable subcontract cost means the
maximum cost to complete the work specified for the subcontract, including the
estimated cost of work to be performed by the subcontractor's own forces, a percentage
for risk contingency, negotiated support services, and approved change orders. The
maximum allowable subcontract cost must be negotiated between the general
contractor/construction manager and the selected firm when the construction documents
and specifications are at least ninety percent complete. Final agreement on the
maximum allowable subcontract cost is subject to the approval of the public body.
(11) If the work of the mechanical contractor or electrical contractor is completed
for less than the maximum allowable subcontract cost, any savings not otherwise
negotiated as part of an incentive clause becomes part of the risk contingency
included in the general contractor/construction manager's maximum allowable
construction cost. If the work of the mechanical contractor or the electrical
contractor is completed for more than the maximum allowable subcontract cost, the
additional cost is the responsibility of that subcontractor. An independent audit,
paid for by the public body, must be conducted to confirm the proper accrual of costs
as outlined in the contract.
(12) A mechanical or electrical contractor selected under this section may perform
work with its own forces. In the event it elects to subcontract some of its work, it
must select a subcontractor utilizing the procedure outlined in RCW 39.10.380.
[ 2013 c 222 § 15; 2010 c 163 § 1.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.390
General contractor/construction manager procedure—Subcontract work.
(1) Except as provided in this section, bidding on subcontract work or for the supply
of equipment or materials by the general contractor/construction manager or its
subsidiaries is prohibited.
(2) The general contractor/construction manager, or its subsidiaries, may bid on
subcontract work or for the supply of equipment or materials if:
(a) The work within the subcontract bid package or equipment or materials is
customarily performed or supplied by the general contractor/construction manager;
(b) The bid opening is managed by the public body and is in compliance with RCW
39.10.380; and
(c) Notification of the general contractor/construction manager's intention to bid is
included in the public solicitation of bids for the bid package or for the equipment
or materials.
(3) In no event may the general contractor/construction manager or its subsidiaries
assign warranty responsibility or the terms of its contract or purchase order with
vendors for equipment or material purchases to subcontract bid package bidders or
subcontractors who have been awarded a contract. The value of subcontract work
performed and equipment and materials supplied by the general contractor/construction
manager may not exceed thirty percent of the negotiated maximum allowable construction
cost, unless procured as a heavy civil construction project under this chapter.
Negotiated support services performed by the general contractor/construction manager
shall not be considered subcontract work for purposes of this subsection. (4)
Notwithstanding any contrary provision of this chapter, for a project that a public
body has elected to procure as a heavy civil construction project under this chapter,
at least thirty percent of the cost of the work to construct the project included in
the negotiated maximum allowable construction cost must be procured through
competitive sealed bidding in which bidding by the general contractor/construction
manager or its subsidiaries is prohibited.
[ 2014 c 42 § 7; 2013 c 222 § 16; 2007 c 494 § 306.]
NOTES: Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.400
General contractor/construction manager procedure—Prebid determination of
subcontractor eligibility.
(1) If determination of subcontractor eligibility prior to seeking bids is in the
best interest of the project and critical to the successful completion of a
subcontract bid package, the general contractor/construction manager and the public
body may determine subcontractor eligibility to bid. The general
contractor/construction manager and the public body must:
(a) Conduct a hearing and provide an opportunity for any interested party to submit
written and verbal comments regarding the justification for conducting bidder
eligibility, the evaluation criteria, and weights for each criteria and subcriteria;
(b) Publish a notice of intent to evaluate and determine bidder eligibility in a
legal newspaper published in or as near as possible to that part of the county where
the public work will be constructed at least fourteen calendar days before conducting
a public hearing;
(c) Ensure the public hearing notice includes the date, time, and location of the
hearing, a statement justifying the basis and need for performing eligibility analysis
before bid opening, and how interested parties may, at least five days before the
hearing, obtain the specific eligibility criteria and applicable weights given to each
criteria and subcriteria that will be used during evaluation;
(d) After the public hearing, consider written and verbal comments received and
determine if establishing bidder eligibility in advance of seeking bids is in the best
interests of the project and critical to the successful completion of a subcontract
bid package; and
(e) Issue a written final determination to all interested parties. All protests of
the decision to establish bidder eligibility before issuing a subcontractor bid
package must be filed with the superior court within seven calendar days of the final
determination. Any modifications to the eligibility criteria and weights shall be
based on comments received during the public hearing process and shall be included in
the final determination.
(2) Determinations of bidder eligibility shall be in accordance with the evaluation
criteria and weights for each criteria established in the final determination and
shall be provided to interested persons upon request. Any potential bidder determined
not to meet eligibility criteria must be afforded one opportunity to establish its
eligibility. Protests concerning bidder eligibility determinations shall be in
accordance with subsection (1) of this section.
[ 2013 c 222 § 17; 2007 c 494 § 307.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.410
General contractor/construction manager procedure—Subcontract agreements.
Subcontract agreements used by the general contractor/construction manager shall not:
(1) Delegate, restrict, or assign the general contractor/construction manager's
implied duty not to hinder or delay the subcontractor. Nothing in this subsection (1)
prohibits the general contractor/construction manager from requiring subcontractors
not to hinder or delay the work of the general contractor/construction manager or
other subcontractors and to hold subcontractors responsible for such damages;
(2) Delegate, restrict, or assign the general contractor/construction manager's
authority to resolve subcontractor conflicts. The general contractor/construction
manager may delegate or assign coordination of specific elements of the work,
including: (a) The coordination of shop drawings among subcontractors; (b) the
coordination among subcontractors in ceiling spaces and mechanical rooms; and (c) the
coordination of a subcontractor's lower tier subcontractors. Nothing in this
subsection prohibits the general contractor/construction manager from imposing a duty
on its subcontractors to cooperate with the general contractor/construction manager
and other subcontractors in the coordination of the work;
(3) Restrict the subcontractor's right to damages for changes to the construction
schedule or work to the extent that the delay or disruption is caused by the general
contractor/construction manager or entities acting for it. The general
contractor/construction manager may require the subcontractor to provide notice that
rescheduling or resequencing will result in delays or additional costs;
(4) Require the subcontractor to bear the cost of trade damage repair except to the
extent the subcontractor is responsible for the damage. Nothing in this subsection (4)
precludes the general contractor/construction manager from requiring the subcontractor
to take reasonable steps to protect the subcontractor's work from trade damage; or
(5) Require the subcontractor to execute progress payment applications that waive
claims for additional time or compensation or bond or retainage rights as a condition
of receipt of progress payment, except to the extent the subcontractor has received or
will receive payment. Nothing in this section precludes the general
contractor/construction manager from requiring the subcontractor to provide notice of
claims for additional time or compensation as a condition precedent to right of
recovery or to execute a full and final release, including a waiver of bond and
retainage rights, as a condition of final payment.
[ 2007 c 494 § 308.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.420
Job order procedure—Public bodies may authorize and use.
(1) All public bodies of the state of Washington are authorized to award job order
contracts and use the job order contracting procedure.
(2)(a) The department of enterprise services may issue job order contract work orders
for Washington state parks department projects and public hospital districts.
(b) The department of enterprise services, the University of Washington, and
Washington State University may issue job order contract work orders for the state
regional universities and The Evergreen State College.
(3) Public bodies may use a job order contract for public works projects when a
determination is made that the use of job order contracts will benefit the public by
providing an effective means of reducing the total lead-time and cost for the
construction of public works projects for repair and renovation required at public
facilities through the use of unit price books and work orders by eliminating
time-consuming, costly aspects of the traditional public works process, which require
separate contracting actions for each small project.
[ 2019 c 212 § 7; 2017 c 136 § 1; 2016 c 52 § 1. Prior: 2013 c 222 § 18; 2013 c 186 §
1; 2012 c 102 § 1; 2009 c 75 § 7; 2007 c 494 § 401; 2003 c 301 § 1. Formerly RCW
39.10.130.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.430
Job order procedure—Contract award process.
(1) Job order contracts shall be awarded through a competitive process using public
requests for proposals.
(2) The public body shall make an effort to solicit proposals from certified minority
or certified woman-owned contractors to the extent permitted by the Washington state
civil rights act, RCW 49.60.400.
(3) The public body shall publish, at least once in a statewide publication and legal
newspaper of general circulation published in every county in which the public works
project is anticipated, a request for proposals for job order contracts and the
availability and location of the request for proposal documents. The public body shall
ensure that the request for proposal documents at a minimum includes:
(a) A detailed description of the scope of the job order contract including
performance, technical requirements and specifications, functional and operational
elements, minimum and maximum work order amounts, duration of the contract, and
options to extend the job order contract;
(b) The reasons for using job order contracts;
(c) A description of the qualifications required of the proposer;
(d) The identity of the specific unit price book to be used; (e) The minimum
contracted amount committed to the selected job order contractor;
(f) A description of the process the public body will use to evaluate qualifications
and proposals, including evaluation factors and the relative weight of factors. The
public body shall ensure that evaluation factors include, but are not limited to,
proposal price and the ability of the proposer to perform the job order contract. In
evaluating the ability of the proposer to perform the job order contract, the public
body may consider: The ability of the professional personnel who will work on the job
order contract; past performance on similar contracts; ability to meet time and budget
requirements; past performance on approved subcontractor inclusion plans; ability to
provide a performance and payment bond for the job order contract; recent, current,
and projected workloads of the proposer; location; and the concept of the proposal;
(g) The form of the contract to be awarded;
(h) The method for pricing renewals of or extensions to the job order contract;
(i) A notice that the proposals are subject to RCW 39.10.470; and
(j) Other information relevant to the project.
(4) A public body shall establish a committee to evaluate the proposals. After the
committee has selected the most qualified finalists, the finalists shall submit final
proposals, including sealed bids based upon the identified unit price book. Such bids
may be in the form of coefficient markups from listed price book costs. The public
body shall award the contract to the firm submitting the highest scored final proposal
using the evaluation factors and the relative weight of factors published in the
public request for proposals and will notify the board of the award of the contract.
(5) The public body shall provide a protest period of at least ten business days
following the day of the announcement of the apparent successful proposal to allow a
protester to file a detailed statement of the grounds of the protest. The public body
shall promptly make a determination on the merits of the protest and provide to all
proposers a written decision of denial or acceptance of the protest. The public body
shall not execute the contract until two business days following the public body's
decision on the protest. (6) The requirements of RCW 39.30.060 do not apply to
requests for proposals for job order contracts.
[ 2019 c 212 § 8; 2007 c 494 § 402.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.440
Job order procedure—Contract requirements.
(1) The maximum total dollar amount that may be awarded under a job order contract is
four million dollars per year for a maximum of three years. Any unused capacity from
the previous year may be carried over for one year and added to the immediate
following year's limit. The maximum annual volume including unused capacity shall not
exceed the limit of two years. The maximum total dollar amount that may be awarded
under a job order contract for the department of enterprise services, counties with a
population of more than one million, and cities with a population of more than four
hundred thousand is six million dollars per year for a maximum of three years. The
maximum total dollar amounts are exclusive of Washington state sales and use tax.
(2) Job order contracts may be executed for an initial contract term of not to exceed
two years, with the option of extending or renewing the job order contract for one
year. All extensions or renewals must be priced as provided in the request for
proposals. The extension or renewal must be mutually agreed to by the public body and
the job order contractor.
(3) A public body may have no more than three job order contracts in effect at any
one time, with the exception of the department of enterprise services, which may have
six job order contracts in effect at any one time.
(4) At least ninety percent of work contained in a job order contract must be
subcontracted to entities other than the job order contractor. The job order
contractor must distribute contracts as equitably as possible among qualified and
available subcontractors including certified minority and woman-owned subcontractors
to the extent permitted by law as demonstrated on the subcontractor and supplier
project submission, and shall limit subcontractor bonding requirements to the greatest
extent possible.
(5) The job order contractor shall publish notification of intent to perform public
works projects at the beginning of each contract year in a statewide publication and
in a legal newspaper of general circulation in every county in which the public works
projects are anticipated.
(6) Job order contractors shall pay prevailing wages for all work that would
otherwise be subject to the requirements of chapter 39.12 RCW. Prevailing wages for
all work performed pursuant to each work order must be the rates in effect at the time
the individual work order is issued.
(7) If, in the initial contract term, the public body, at no fault of the job order
contractor, fails to issue the minimum amount of work orders stated in the public
request for proposals, the public body shall pay the contractor an amount equal to the
difference between the minimum work order amount and the actual total of the work
orders issued multiplied by an appropriate percentage for overhead and profit
contained in the contract award coefficient for services as specified in the request
for proposals. This is the contractor's sole remedy.
(8) All job order contracts awarded under this section must be signed before July 1,
2021; however the job order contract may be extended or renewed as provided for in
this section.
(9) Public bodies may amend job order contracts awarded prior to July 1, 2007, in
accordance with this chapter.
[ 2019 c 212 § 9; 2015 c 173 § 1; 2013 c 222 § 19; 2007 c 494 § 403.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
RCW 39.10.450
Job order procedure—Work orders.
(1) The maximum dollar amount for a work order is five hundred thousand dollars,
excluding Washington state sales and use tax.
(2) All work orders issued for the same project shall be treated as a single work
order for purposes of the dollar limit on work orders.
(3) No more than twenty percent of the dollar value of a work order may consist of
items of work not contained in the unit price book.
(4) Any new stand-alone permanent structure constructed under a work order shall not
exceed three thousand gross square feet.
(5) A public body may issue no work orders under a job order contract until it has
approved, in consultation with the office of minority and women's business enterprises
or the equivalent local agency, a plan prepared by the job order contractor that
equitably spreads certified women and minority business enterprise subcontracting
opportunities, to the extent permitted by the Washington state civil rights act, RCW
49.60.400, among the various subcontract disciplines.
(6) For purposes of chapters 39.08, 39.12, 39.76, and 60.28 RCW, each work order
issued shall be treated as a separate contract. The alternate filing provisions of RCW
39.12.040(2) apply to each work order that otherwise meets the eligibility
requirements of RCW 39.12.040(2).
(7) The job order contract shall not be used for the procurement of architectural or
engineering services not associated with specific work orders. Architectural and
engineering services shall be procured in accordance with RCW 39.80.040.
(8) Any work order over three hundred fifty thousand dollars, excluding Washington
state sales and use tax, and including over six hundred single trade hours shall
utilize a state registered apprenticeship program for that single trade in accordance
with RCW 39.04.320. Awarding entities may adjust this requirement for a specific work
order for the following reasons:
(a) The demonstrated lack of availability of apprentices in specific geographic
areas;
(b) A disproportionately high ratio of material costs to labor hours, which does not
make feasible the required minimum levels of apprentice participation;
(c) Participating contractors have demonstrated a good faith effort to comply with
the requirements of RCW 39.04.300 and 39.04.310; or
(d) Other criteria the awarding entity deems appropriate.
[ 2019 c 212 § 10; 2012 c 102 § 2; 2007 c 494 § 404.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.460
Job order procedure—Required information to board.
Each year, a public body shall provide to the board the following information for
each job order contract for the period July 1st through June 30th:
(1) A list of work orders issued;
(2) The cost of each work order;
(3) A list of subcontractors hired under each work order;
(4) If requested by the board, a copy of the intent to pay prevailing wage and the
affidavit of wages paid for each work order subcontract; and
(5) Any other information requested by the board.
[ 2012 c 102 § 3; 2007 c 494 § 405.]
NOTES: Sunset Act application: See note following chapter digest.
RCW 39.10.470
Public inspection of certain records—Protection of trade secrets—Protection of
documents submitted.
(1) Except as provided in subsections (2) and (3) of this section, all proceedings,
records, contracts, and other public records relating to alternative public works
transactions under this chapter shall be open to the inspection of any interested
person, firm, or corporation in accordance with chapter 42.56 RCW.
(2) Trade secrets, as defined in RCW 19.108.010, or other proprietary information
submitted by a bidder, offeror, or contractor in connection with an alternative public
works transaction under this chapter shall not be subject to chapter 42.56 RCW if the
bidder, offeror, or contractor specifically states in writing the reasons why
protection is necessary, and identifies the data or materials to be protected.
(3) All documents related to a procurement under RCW 39.10.330 are exempt from
disclosure until the notification of the highest scoring finalist is made in
accordance with RCW 39.10.330(6) or the selection process is terminated, except as
expressly required under RCW 39.10.330(3).
[ 2019 c 212 § 11; 2014 c 19 § 2; 2005 c 274 § 275; 1994 c 132 § 10. Formerly RCW
39.10.100.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.480
Construction of chapter—Waiver of other limits and requirements.
This chapter shall not be construed to affect or modify the existing statutory,
regulatory, or charter powers of public bodies except to the extent that a procedure
authorized by this chapter is adopted by a public body for a particular public works
project. In that event, the normal contracting or procurement limits or requirements
of a public body as imposed by statute, ordinance, resolution, or regulation shall be
deemed waived or amended only to the extent necessary to accommodate such procedures
for a particular public works project.
[ 1994 c 132 § 9. Formerly RCW 39.10.090.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.490
Application of chapter.
The alternative public works contracting procedures authorized under this chapter are
limited to public works contracts signed before July 1, 2021. Methods of public works
contracting authorized under this chapter shall remain in full force and effect until
completion of contracts signed before July 1, 2021.
[ 2013 c 222 § 20; 2007 c 494 § 501; 2001 c 328 § 5. Prior: 1997 c 376 § 7; 1997 c
220 § 404 (Referendum Bill No. 48, approved June 17, 1997); 1995 3rd sp.s. c 1 § 305;
1994 c 132 § 12. Formerly RCW 39.10.120.]
NOTES:
Sunset Act application: See note following chapter digest.
Effective date—2013 c 222: See note following RCW 39.10.210.
Effective date—2001 c 328: See note following RCW 39.10.210.
Effective date—1997 c 376: See note following RCW 39.10.210.
Referendum—Other legislation limited—Legislators' personal intent not
indicated—Reimbursements for election—Voters' pamphlet, election requirements—1997 c
220: See RCW 36.102.800 through 36.102.803.
Part headings not law—Effective date—1995 3rd sp.s. c 1: See notes following RCW
82.14.0485.
RCW 39.10.900
Captions not law—1994 c 132.
Captions as used in this act do not constitute any part of law.
[ 1994 c 132 § 13.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.901
Severability—1994 c 132.
If any provision of this act or its application to any person or circumstance is held
invalid, the remainder of the act or the application of the provision to other persons
or circumstances is not affected.
[ 1994 c 132 § 14.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.903
Part headings and captions not law—2007 c 494.
Part headings and captions used in chapter 494, Laws of 2007 are not any part of the
law.
[ 2007 c 494 § 510.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.904
Effective dates—2007 c 494.
This act is necessary for the immediate preservation of the public peace, health, or
safety, or support of the state government and its existing public institutions, and
takes effect July 1, 2007, except for section 104 of this act, which takes effect
immediately [May 15, 2007], and section 508 of this act, which takes effect June 30,
2007.
[ 2007 c 494 § 512.]
NOTES:
Sunset Act application: See note following chapter digest.
RCW 39.10.905
Severability—2007 c 494.
If any provision of this act or its application to any person or circumstance is held
invalid, the remainder of the act or the application of the provision to other persons
or circumstances is not affected.
[ 2007 c 494 § 513.]
NOTES:
Sunset Act application: See note following chapter digest.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Recommendations & Responses
Legislative Auditor Recommendation
The Legislative Auditor recommends continuing authorization of
alternative public works contracting methods
Without legislative action, RCW 39.10 will terminate on June 30, 2021.
Recommendation #1: The Legislature should continue the alternative contracting
methods in RCW 39.10
If the Legislature continues the alternative contracting statutes, it should consider
whether to extend them permanently or extend the sunset to a future date.
Legislation Required:
Yes. Without legislative action RCW 39.10 will expire on June 30, 2021.
Fiscal Impact:
No additional impact beyond what is currently funded through DES. In the 2017-19
biennium, expenditures to support CPARB were $281,330.
Recommendation #2: CPARB should evaluate which JOC data it needs to perform its
functions and propose appropriate modifications to the Legislature
CPARB has engaged stakeholders to address issues of concern in public works
contracting and obtained information to develop and recommend policies to the
Legislature to enhance the quality, efficiency, and accountability of public works
projects. Given this role and challenges in collecting complete and accurate JOC data,
CPARB should evaluate what JOC data it needs to perform its functions and propose
appropriate modifications to the Legislature.
Legislation Required:
No
Fiscal Impact:
JLARC staff assume this can be accomplished within existing resources.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Recommendations & Responses
CPARB Response
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Recommendations & Responses
DES Response
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Recommendations & Responses
OFM Response
The Office of Financial Management (OFM) was given an opportunity to comment on this report. OFM responded that it does not have any comments.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
Recommendations & Responses
Current Recommendation Status
JLARC staff follow up with agencies on Legislative Auditor recommendations for 4
years. Responses from agencies on the latest status of implementing recommendations
for this report will be available in 2022.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
More About This Review
Audit Authority
The Joint Legislative Audit and Review Committee (JLARC) works to make state government operations more efficient and effective. The Committee is comprised of an equal number of House members and Senators, Democrats and Republicans.
JLARC's non-partisan staff auditors, under the direction of the Legislative Auditor, conduct performance audits, program evaluations, sunset reviews, and other analyses assigned by the Legislature and the Committee.
The statutory authority for JLARC, established in Chapter 44.28 RCW,
requires the Legislative Auditor to ensure that JLARC studies are conducted in
accordance with Generally Accepted Government Auditing Standards, as applicable to the
scope of the audit. This study was conducted in accordance with those applicable
standards. Those standards require auditors to plan and perform audits to obtain
sufficient, appropriate evidence to provide a reasonable basis for findings and
conclusions based on the audit objectives. The evidence obtained for this JLARC report
provides a reasonable basis for the enclosed findings and conclusions, and any
exceptions to the application of audit standards have been explicitly disclosed in the
body of this report.
Committee Action to Distribute Report
On December 7, 2020 this report was approved for distribution by the Joint Legislative Audit and Review Committee.
Action to distribute this report does not imply the Committee agrees or disagrees with Legislative Auditor recommendations.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
More About This Review
Study Questions
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review
December 2020
More About This Review
Methodology
The methodology JLARC staff use when conducting analyses is tailored to the scope of each study, but generally includes the following:
Interviews with stakeholders, agency representatives, and other
relevant organizations or individuals.
Site visits to entities that are under review.
Document reviews, including applicable laws and regulations, agency
policies and procedures pertaining to study objectives, and published reports,
audits or studies on relevant topics.
Data analysis, which may include data collected by agencies and/or
data compiled by JLARC staff. Data collection sometimes involves surveys or focus
groups.
Consultation with experts when warranted. JLARC staff consult with
technical experts when necessary to plan our work, to obtain specialized analysis
from experts in the field, and to verify results.
The methods used in this study were conducted in accordance with Generally Accepted Government Auditing Standards.
More details about specific methods related to individual study objectives are described in the body of the report under the report details tab or in technical appendices.
20-06
Final Report | Alternative Public Works Contracting Procedures Sunset
Review