Deferral use has been infrequent and concentrated in five local
governments, with few adverse effects. Financial benefit of deferrals could increase if
market conditions change in the future.
December 2021
Executive Summary
The 2015 Legislature required counties, cities, and towns that collect impact fees
for new single-family residential construction to adopt a fee deferral process. The
fee deferral allows builders to pay impact fees near the end of the construction
process rather than at the beginning. The Legislature also required the Joint
Legislative Audit and Review Committee (JLARC) to collect data on the use and cost of
deferral programs and to review implementation of impact fee deferrals.
Impact fee deferral programs vary, as allowed by state law
JLARC staff identified 107 local governments that collect impact fees and are
required to have deferral programs in place. Of those, 98 local governments
implemented a deferral program and nine did not.
The law allows local governments to decide when to collect deferred impact fees,
whether to charge administrative fees, and whether to limit the deferral to the first
20 building permits per builder.
Local governments implemented programs using different combinations of these three
factors. As a result, deferral programs vary among local governments.
Deferral use has been infrequent and concentrated in five local governments
Deferrals were issued by 22 local governments
Builders requested and received 3,741 deferrals from 22 of the 98 local governments
that offered them. Five local governments — Redmond, La Center, Ridgefield, Ferndale,
and Kitsap County — issued 91% of all deferrals.
Data indicates that deferral use has been infrequent and unrelated to permit
activity. Builders requested deferrals on less than 5% of the permits issued for
single-family homes in cities and counties with deferral programs.
Local governments report that 99.9% of deferred fees were repaid on time
Local governments reported few issues with unpaid deferrals. In 2018 and 2019,
builders deferred $11 million out of $323 million in impact fees. All but $13,000 was
repaid on time.
State law mandates that local governments require builders to place a lien on the
property equal to the amount of deferred fees. This lien requirement was meant to
protect local governments from builders defaulting, foreclosing, or failing to pay
deferred fees.
Local governments have implemented other controls, such as withholding final
inspection or certificate of occupancy, to ensure deferred fees are paid. Further,
stakeholders report that impact fee liens add time, uncertainty, and costs to the
deferral process. The five local governments with the most deferrals do not require
liens, primarily due to a grandfathering provision for deferral programs that predate
the 2015 law.
Builders report that several factors influence their decision to defer impact fees
and indicate that deferrals may become more attractive in a less favorable
economy
JLARC staff modeled the financial benefit of deferring fees in the 98 local
governments with deferral programs. The model indicated that deferrals offer greater
savings to builders if impact fee amounts and interest rates are high and deferral
periods are long.
In today's housing market, however, interest rates are low and deferral periods are
short. As a result, models estimate current cost savings of no more than $1,500 per
home. In many instances, administrative fees for deferrals cost more than the savings
from the deferral.
Builders reported that other factors, including staff time, attorney costs, and the
impact of liens on available financing also influence the decision to defer fees.
However, builders and other stakeholders report that impact fee deferrals may be a
valuable tool in the future, particularly if interest rates increase and houses do not
sell as quickly.
Department of Commerce directed to monitor future use of deferrals
Statute requires the Department of Commerce (Commerce) to report the number of
deferrals requested, issued, and not paid.
If the Legislature wants information about whether deferral use and costs change in
the future, Commerce will need to collect information not currently required by
statute. However, since deferrals are not widely used and there have been few issues
for local governments, ongoing monitoring by Commerce may be unnecessary.
Legislative Auditor Recommendations
The Legislative Auditor makes three recommendations:
Cities without a deferral program should pass an ordinance to adopt and maintain
an impact fee deferral program for single-family residential construction as
required by statute.
The Legislature should consider whether liens are a necessary tool to ensure that
deferred fees are paid.
The Legislature should either repeal Commerce's data collection or identify which
measures Commerce should collect that would be helpful for evaluating program
use.
Several cities and agencies formally responded and either concurred, partially
concurred, or did not concur with the Legislative Auditor's recommendations. You can
find responses, the Legislative Auditor's response to City of Everson comments, and additional
information in Recommendations.
Committee Action to Distribute Report
On December 1, 2021 this report was approved for distribution by the Joint
Legislative Audit and Review Committee. Action to distribute this report does not
imply the Committee agrees or disagrees with Legislative Auditor recommendations.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
1. Deferral programs vary
Impact fee deferral programs vary, as allowed by state law
Local governments collect impact fees to finance public facilities such as road
improvements, schools, and parks
Cities, counties, and towns that plan under the Growth Management Act (GMA) are
authorized to collect impact fees on new development. Impact fees are one-time charges
assessed by local governments to help finance public facilities that will serve the new
development. Under state law (RCW 82.02.050), impact fees can be used to pay for
schools, parks and open spaces, transportation (road improvements), and new fire
facilities.
Local governments are authorized to impose up to four different types of impact fees.
The fees vary based upon need and local conditions. For example, the city of Deer Park
collects only transportation impact fees, which cost $350 per single-family home,
whereas the city of Issaquah collects all four types of impact fees, which cost a total
of $38,705 per single-family home. Appendix
A shows the type and amounts of impact fees charged by each city.
Local governments must allow builders to defer impact fees on new single-family
homes
In 2015, the Legislature required counties, cities, and towns that collect impact fees
for new single-family residential construction to adopt a deferral program.
Key provisions of the law include:
Deferral programs must be implemented by September 1, 2016.
Deferrals must be available upon request from the builder.
Local governments can defer payments until final inspection, issuance of certificate
of occupancy, or the closing of the first sale of the property. However, the deferral
can be no longer than 18 months from the time the building permit is issued.
The builder must grant and record a lien against the property in favor of the
municipality equal to the amount of the deferred impact fee.
The impact fee amount that the builder pays must reflect the fees in place when they
applied for a deferral.
Local governments that had a deferral system in effect on or before April 1, 2015 are
exempt from many of the law's provisions. The relevant sections of statute are in Appendix
C.
98 out of 107 local governments have a deferral program as required by law
Exhibit 1.1: 98 local governments have a deferral program. Nine do not.
Source: Local government municipal codes.
JLARC staff identified 107 local governments that are required to have a deferral
program in place because they collect impact fees.
98 of the 107 local governments have a deferral program. This includes 92 cities or
towns and 6 counties (Clark, King, Kitsap, Pierce, Snohomish, Thurston).
Of the 98, two cities have implemented partial deferral programs. Black Diamond
collects school and fire impact fees, but allows deferral only for school impact fees.
Pacific collects impact fees for parks and road improvements, but only road fees may
be deferred.
18 of the 98 local governments had a deferral system in effect on or before April 1,
2015.
Nine cities have not yet implemented a deferral program
Nine cities and towns do not appear to have a deferral program.
In response to inquiries from JLARC staff:
Deer Park confirmed it does not have a deferral program.
Granite Falls, Maple Valley, and Everson report that they are in the process of
developing programs.
Algona, Carbonado, Gold Bar, Nooksack and Roy did not respond to inquiries about the
status of their deferral programs.
Statute provided local governments with options in developing deferral programs
The law allows local governments establishing new deferral programs to decide:
When to collect impact fees.
Whether to impose a reasonable administrative fee.
Whether to limit the deferral to the first 20 building permits per builder per year.
Local governments implemented programs using different combinations of these three
factors. As a result, deferral programs vary among local governments.
Exhibit 1.2: Deferral programs vary in terms of timing, fees, and limits
Source: JLARC staff analysis of local governments' deferral programs.
The cost of administrative fees also varies
Statute authorizes local governments to collect reasonable administrative fees to cover
the costs associated with reviewing and processing impact fee deferrals. Statute
provides local governments the discretion to determine what costs are considered
reasonable.
Sixty local governments charge administrative fees, which range from $50 to $1,200
per single-family home. The median fee is $200.
Some charge additional hourly fees for lengthy deferral applications.
In addition to administrative fees, deferral applicants also must pay a fee when they
record a lien and another fee when they request release of the lien. In most counties,
lien recording and release fees are $39 each, plus more for multi-page documents.
Legislative Auditor recommendation
Cities without a deferral program should pass an ordinance to adopt and maintain an
impact fee deferral program for single-family residential construction as required by
statute. You can find additional information in Recommendations.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
2. Deferral use has been infrequent
Deferrals account for a small portion of all single-family
building permits issued. Five local governments that have similar programs issued 91% of
deferrals.
Twenty-two local governments issued deferrals. Of these, five issued
91% of deferrals.
Between 2018 and 2019, 22 local governments issued deferrals
Builders requested and received 3,741 deferrals from 22 local governments. This
includes:
1,236 park impact fee deferrals.
1,189 traffic impact fee deferrals.
1,109 school impact fee deferrals.
207 fire impact fee deferrals.
Local governments did not report rejecting any applications.
Among the 76 other local governments that have deferral programs, 66 reported that they
did not issue any deferrals and 10 did not respond to the JLARC staff request for
information.
Five local governments issued 91% of deferrals
Ferndale, La Center, Redmond, Ridgefield, and Kitsap County issued 91% of deferrals.
JLARC staff found that their deferral programs have the following in common:
Except for Ridgefield, the local governments established their deferral programs
before passage of ESB 5923 in 2015 and were exempt from many of the law's requirements
due to a grandfathering provision.
Local government staff believe their programs are successful because they worked
with the building groups in the community.
The local governments do not require a lien for impact fee deferrals.
The local governments do not charge administrative fees for impact fee
deferrals.
Staff integrated the deferral application into the building permit application so
there are no additional steps, paperwork, or applications to complete.
Builders requested few deferrals from local governments that charge fees and require
liens
Builders reported that they might avoid deferring impact fees if the process were
complicated, time-consuming, or expensive. Most local governments require builders
to:
Request a deferral before the building permit is issued. Depending on the local
governments, builders can request a deferral verbally, in writing, or online.
Complete a separate deferral application form and pay an administrative fee for each
single-family residence deferral.
Sign and record a deferred impact fee lien for each single-family residence deferral
before the building permit is issued.
Deferral use is infrequent and appears unrelated to the amount of home
construction
Data indicates that deferral use has been infrequent and unrelated to permit activity.
JLARC staff estimate that builders requested deferrals on 1,284
permitsOne permit could have up to four impact fees
deferred (school, park, transportation, fire). , which is less than 5%
of the estimated 26,990 permits issued for single-family homes by the 98 local
governments with deferral programs. In addition:
Of the five local governments that issued the most single-family building permits,
only one issued any deferrals.
The five local governments that issued the most deferrals issued only 8% of
single-family building permits.
Exhibit 2.1: Permits and deferrals appear unrelated
Source: JLARC staff analysis of local government data and US Census' Building Permit
Survey.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
3. Deferrals repaid on time
Local governments report that 99.9% of deferrals were repaid on
time and that capital improvement projects have not been affected
Local governments report that 3 out of 3,741 deferrals were not fully and timely paid
JLARC staff analyzed 2018-2019 data provided by local governments and found that:
Three out of the 3,741 deferrals were not paid on time or in full.
$11 million out of approximately $323 million in impact fees was deferred.
$13,000 of $11 million in deferred fees was not paid on time or in full.
To ensure deferrals are fully and timely paid, local governments report that they have
implemented controls over the tracking and collection of deferred impact fees. These
include the ability to withhold final inspections and certificates of occupancy until
deferred fees are paid.
Exhibit 3.1 Local governments implemented internal controls to ensure payment of
deferred fees
Source: JLARC staff summary of permitting and deferral processes.
Capital improvements have not been affected
Local governments, school districts, and fire districts told JLARC staff that deferrals
have not caused delays in capital improvement planning or construction.
According to statute, local governments may not rely solely on impact fees to finance
public improvements and must balance impact fees with other public funds. Further, they
must consider other public funding sources when establishing their impact fee schedules.
Stakeholders reported that impact fees comprise a relatively small portion of overall
expenditures for capital improvements. Central Kitsap School District, for example,
reported that impact fees provide $210,000 of the $3 to $5 million needed for capital
projects each year, or 4.2% to 7%.
Local governments report that the impact to staff resources has been minimal
Local governments reported that while they did not track the costs of administering
deferral programs, the impact to staff resources has been minimal. Some respondents
provided reasons for this including:
Integrating impact fee deferral tracking and collection into their regular building
permit and inspection process avoided additional costs.
Deferrals are not widely used, mitigating the time and resources needed to complete
additional paperwork and reviews.
While there were initial costs to establish deferral programs, the ongoing costs
have been minimal.
Because few deferrals were not paid on time or in full, local governments did not
have to spend staff time and resources collecting delinquent payments.
Stakeholders report that the lien requirement was intended to protect their interests,
but may be unnecessary or problematic
By law, local governments must require builders to record a lien against the property
in the amount of the deferred impact fees. Local governments that established programs
before the 2015 legislation are exempt from this requirement.
JLARC staff interviewed and corresponded with 52 stakeholders from local governments,
lenders, and builders to better understand how deferral programs worked in practice.
Eight of the 52 stakeholders either support the lien requirement or view it
neutrally. The eight included lenders, cities, school districts, and builders.
26 stakeholders (including most of the builders, almost all of the lenders, and the
five local governments that have issued the most deferrals) stated that the lien was
unnecessary, an obstacle, or that it discouraged builders from pursuing
deferrals.
The remaining 18 stakeholders did not provide feedback on impact fee deferral
liens.
Liens are one of many controls to protect local government interests
Stakeholders that support the liens noted that it is meant to protect local governments
from builders defaulting, foreclosing, or failing to pay deferred fees. Others report
that the lien is likely unnecessary because other controls (e.g., withholding final
inspection or certificates of occupancy) protect the governments' interests.
Furthermore, lenders require a certificate of occupancy before converting a construction
loan to a traditional mortgage for the purpose of selling the house. JLARC staff learned
of only one instance when the lien was used to ensure payment of deferred fees.
Stakeholders cited multiple reasons that liens may be problematic
The lien may deter builders from requesting a deferral. Stakeholders reported
that builders were apprehensive about recording liens against the property in favor of
the city and would forgo deferring impact fees once they learned that a lien was
required. Bellingham reported that builders abandoned six deferral requests because of
the lien requirement.
The lien may require extra time and resources to process, record, and track.
Some local governments reported that they do not want to require liens because of the
strain it puts on resources. For example, Ridgefield reported that its staff learned
from other local governments that the lien requirement was cumbersome and time
consuming. Although the city implemented its deferral program after the state
directive, it did not include a lien requirement because it could cost money for both
the city and the builders.
The lien may complicate and delay construction financing. Most lenders said
builders must meet special conditions before they will finance a project with an
impact fee lien. These conditions include ensuring that the cost of the deferred fees
is included in the construction budget and the builder is in good standing with the
lender. Lenders also reported that banks and title companies often require additional
approvals before the lien is recorded, which can delay financing.
The deferral lien may take priority over the mortgage lien in foreclosure
proceedings. Another condition for construction financing is that, in the case
of foreclosure, the lien must have lower priority for repayment than the mortgage.
However, a general rule in property lawCommonly known as "first in time, first in right." says that the
lien recorded first takes higher priority. Since the impact fee lien is often recorded
before the mortgage lien, it is difficult for builders to meet this condition.
The lien may delay sale. Lenders stated that liens also may delay the sale of
the house. Additionally, it may take several days or weeks for a local government to
release the lien after the deferred fees are paid, further delaying the sale.
Four local governments do not require liens, despite the mandate to do so
The cities of Brier, Ridgefield, Fife, and Burlington implemented a deferral program
after the 2015 legislation and do not require liens as part of their deferral process.
City staff report that because they are able to withhold final inspection or certificate
of occupancy until the deferred fees are paid, their risk of securing payment is
significantly reduced. City staff believe that the processes and internal controls they
implemented as part of the deferral program eliminated the need for a lien.
Legislative Auditor recommendation
The Legislature should consider whether liens are a necessary tool to ensure that
deferred fees are paid. You can find additional information in Recommendations.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
4. Financial benefit of deferrals could increase in the future
In today's housing market, models estimate cost savings of no
more than $1,500 per home. Deferrals could have greater benefit in the future.
There may be a financial benefit to builders who defer impact fees
Impact fees are collected from builders when the building permit is issued. Builders
that do not defer impact fees typically finance them with a construction loan or pay
them out of pocket. If they finance the fees, builders must pay interest on the loan
until the house is sold. Deferring impact fees allows builders to delay paying impact
fees upfront, which can save money by reducing finance costs.
Financial benefit varies depending upon market conditions and city administrative
fees
Exhibit 4.1: Four factors influence the financial benefit of deferrals
There are four major factors that influence the financial benefit of deferring impact
fees: amount of the impact fees, interest rates, deferral period (how long the builder
defers fees), and the administrative and lien fees.
JLARC staff created a model that shows how the financial benefit changes as these
variables change. In general, the model indicates that:
If impact fee amounts, interest rates, and/or the deferral period increase, builders
will likely have greater financial benefit.
The amount of financial benefit can fall depending on the amount of the
administrative and lien fees.
JLARC staff also modeled the financial benefit of deferring fees for the 98 local
governments with deferral programs. The estimates created by the model use a range of
interest rates and deferral periods.
The analysis suggests that builders benefit from deferring impact fees in more cities
and counties when interest rates and deferral periods increase. For example, as shown in
Exhibit 4.2:
Assuming a 4.25% interest rate and a 9-month deferral period, the model predicted at
least some financial benefit if builders deferred fees in 63 local governments.
Holding the interest rate at 4.25% and increasing the deferral period to 18 months,
the model predicted that there would be a financial benefit to builders who deferred
fees in 82 local governments.
Assuming a 10% interest rate and an 18-month deferral period, the model predicted
that there would be a financial benefit to builders who deferred fees in 94 local
governments.
An interactive version of the model is available in Appendix
B.
Exhibit 4.2: Builders receive greater financial benefit from deferrals in more local
governments when interest rates and deferral periods increase
Source: JLARC staff analysis of the costs and benefits of deferring fees in 98 local
governments.
In today's housing market, cost savings from deferrals are minimal
In today's housing market, lenders and builders report that the current interest rate
on construction loans is between 4.25% and 6% and that single-family homes are built and
sold within 9 months of receiving a building permit. Using these assumptions, JLARC
staff modeled the estimated savings a builder may realize from deferring the payment of
impact fees:
Assuming a 4.25% interest rate, the model estimates a maximum benefit of $998 per
home.
If the interest rate is at 6%, the model estimates a maximum benefit of $1,500 per
home.
For Kitsap County, which has issued the most deferrals, the model predicts a savings
of between $89 and $181 per home.
Builders report that other factors influence their decision to defer
Builders reported additional costs that are not in the model. These costs, which could
reduce or eliminate the financial benefit, include:
Staff time and resources to complete deferral applications.
Travel time to record liens.
Attorney and consultant costs to review deferral and lien documents.
In addition, there are non-cost factors that may influence a builder's decision to
defer:
Construction lenders may be unwilling to finance loans in which liens are recorded
against their properties.
Obtaining a lien release may delay the sale of a house. A builder may be unwilling
to risk delays for a deferral.
In interviews, several builders and lenders noted that impact fee deferrals have not
been appealing because of the additional costs, time, resources, and risks to financing
and sale.
Builders suggested that deferring fees may be more attractive in a less favorable
economy
In the current housing market, houses are selling rapidly. The Washington Center for
Real Estate Research reports that there is low housing inventory and high demand for
homes.
Builders and construction lenders also report that interest rates for construction
loans are low. The prime rate, which lenders use to set the interest rates for
construction loans, is the lowest it has been since the law requiring deferral programs
went into effect. Because financing costs are low, the savings from deferring impact
fees may be negligible.
Nevertheless, builders assert that the option to defer impact fees remains valuable.
Although not widely used now, deferrals may be more appealing in the future,
particularly if interest rates increase and houses do not sell as quickly.
Department of Commerce directed to monitor future use of deferrals
The Legislature directed the Department of Commerce (Commerce) to collect and report
information about the number of deferrals requested, issued, and not paid on time or in
full.
If the Legislature wants information about whether deferral use and costs change in the
future, Commerce will need to collect information not currently required by statute.
This includes administrative costs, amount deferred, and the amount not paid on time or
in full. However, since deferrals are not widely used and there have been few issues for
local governments, ongoing monitoring by Commerce may be unnecessary.
Legislative Auditor recommendation
The Legislature should either repeal Commerce's data collection or identify which
measures Commerce should collect that would be helpful for evaluating program use. You
can find additional information in Recommendations.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
Appendix A: Local Government Impact Fees & Deferrals
Total impact fees vary widely among local governments, from $500
to $38,705
The following table contains impact fee amounts and the number of deferrals issued by
local governments. Data was obtained from local government municipal codes and fee
schedules. In some instances, impact fees vary within a city or county depending on
location or may vary depending on housing size. In those instances, JLARC staff
calculated average fee amounts or assumed typical housing sizes.
JLARC staff identified 107 local governments that collect impact fees, 98 of which
have established deferral programs.
Local governments reported the number of deferrals issued in 2018 and 2019 in
response to JLARC staff surveys and information requests. Ten local governments did
not respond to requests for information.
Click the image below to use the interactive dashboard.
Exhibit A1: Impact fees and deferrals
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
Appendix B: Impact Fee Savings Calculator
Financial benefit from deferral varies depending upon market
conditions and city administrative fees
The following dashboard models the financial benefit of deferring impact fees in the
98 local governments with deferral programs.
There are four major factors that influence the financial benefit of deferring impact
fees: administrative and lien fees, amount of the impact fees, interest rates, and
deferral period (how long the builder defers fees).
Impact fee amounts and the costs to defer were collected from local government codes
and fee schedules. Fees may be deferred until final inspection, certificate of
occupancy, or the first sale of the house, but no longer than 18 months from the
issuance of the building permit.
How to read the chart
The chart illustrates the predicted net benefit or loss from deferring fees in each
of the 98 local governments.
Each circle represents a local government with a deferral program.
In circles to the right of the breakeven point ($0.00), deferring fees may provide
at least some benefit.
In circles to the left of the line, the costs of using the deferral outweigh the
savings gained from it.
The model does not include additional costs incurred by builders, such as staff
time or legal costs, that may reduce the financial benefit of deferring impact
fees.
Click the image below to view the interactive model.
Exhibit B1: Impact fee savings calculator
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Report Details
Appendix C: Applicable statutes
RCW 82.02.050, RCW 44.28.812, RCW 43.31.980
Impact fees—Intent—Limitations.
RCW 82.02.050
(1) It is the intent of the legislature:
(a) To ensure that adequate facilities are available to serve new growth and
development;
(b) To promote orderly growth and development by establishing standards by which
counties, cities, and towns may require, by ordinance, that new growth and development
pay a proportionate share of the cost of new facilities needed to serve new growth and
development; and
(c) To ensure that impact fees are imposed through established procedures and
criteria so that specific developments do not pay arbitrary fees or duplicative fees
for the same impact.
(2) Counties, cities, and towns that are required or choose to plan under RCW
36.70A.040 are authorized to impose impact fees on development activity as part of the
financing for public facilities, provided that the financing for system improvements
to serve new development must provide for a balance between impact fees and other
sources of public funds and cannot rely solely on impact fees.
(3)(a)(i) Counties, cities, and towns collecting impact fees must, by September 1,
2016, adopt and maintain a system for the deferred collection of impact fees for
single-family detached and attached residential construction. The deferral system must
include a process by which an applicant for a building permit for a single-family
detached or attached residence may request a deferral of the full impact fee payment.
The deferral system offered by a county, city, or town under this subsection (3) must
include one or more of the following options:
(A) Deferring collection of the impact fee payment until final inspection;
(B) Deferring collection of the impact fee payment until certificate of occupancy or
equivalent certification; or
(C) Deferring collection of the impact fee payment until the time of closing of the
first sale of the property occurring after the issuance of the applicable building
permit.
(ii) Counties, cities, and towns utilizing the deferral process required by this
subsection (3)(a) may withhold certification of final inspection, certificate of
occupancy, or equivalent certification until the impact fees have been paid in full.
(iii) The amount of impact fees that may be deferred under this subsection (3) must
be determined by the fees in effect at the time the applicant applies for a deferral.
(iv) Unless an agreement to the contrary is reached between the buyer and seller, the
payment of impact fees due at closing of a sale must be made from the seller's
proceeds. In the absence of an agreement to the contrary, the seller bears strict
liability for the payment of the impact fees.
(b) The term of an impact fee deferral under this subsection (3) may not exceed
eighteen months from the date of building permit issuance.
(c) Except as may otherwise be authorized in accordance with (f) of this subsection
(3), an applicant seeking a deferral under this subsection (3) must grant and record a
deferred impact fee lien against the property in favor of the county, city, or town in
the amount of the deferred impact fee. The deferred impact fee lien, which must
include the legal description, tax account number, and address of the property, must
also be:
(i) In a form approved by the county, city, or town;
(ii) Signed by all owners of the property, with all signatures acknowledged as
required for a deed, and recorded in the county where the property is located;
(iii) Binding on all successors in title after the recordation; and
(iv) Junior and subordinate to one mortgage for the purpose of construction upon the
same real property granted by the person who applied for the deferral of impact fees.
(d)(i) If impact fees are not paid in accordance with a deferral authorized by this
subsection (3), and in accordance with the term provisions established in (b) of this
subsection (3), the county, city, or town may institute foreclosure proceedings in
accordance with chapter 61.12 RCW.
(ii) If the county, city, or town does not institute foreclosure proceedings for
unpaid school impact fees within forty-five days after receiving notice from a school
district requesting that it do so, the district may institute foreclosure proceedings
with respect to the unpaid impact fees.
(e)(i) Upon receipt of final payment of all deferred impact fees for a property, the
county, city, or town must execute a release of deferred impact fee lien for the
property. The property owner at the time of the release, at his or her expense, is
responsible for recording the lien release.
(ii) The extinguishment of a deferred impact fee lien by the foreclosure of a lien
having priority does not affect the obligation to pay the impact fees as a condition
of final inspection, certificate of occupancy, or equivalent certification, or at the
time of closing of the first sale.
(f) A county, city, or town with an impact fee deferral process on or before April 1,
2015, is exempt from the requirements of this subsection (3) if the deferral process
delays all impact fees and remains in effect after September 1, 2016.
(g)(i) Each applicant for a single-family residential construction permit, in
accordance with his or her contractor registration number or other unique
identification number, is entitled to annually receive deferrals under this subsection
(3) for the first twenty single-family residential construction building permits per
county, city, or town. A county, city, or town, however, may elect, by ordinance, to
defer more than twenty single-family residential construction building permits for an
applicant. If the county, city, or town collects impact fees on behalf of one or more
school districts for which the collection of impact fees could be delayed, the county,
city, or town must consult with the district or districts about the additional
deferrals. A county, city, or town considering additional deferrals must give
substantial weight to recommendations of each applicable school district regarding the
number of additional deferrals. If the county, city, or town disagrees with the
recommendations of one or more school districts, the county, city, or town must
provide the district or districts with a written rationale for its decision.
(ii) For purposes of this subsection (3)(g), an "applicant" includes an entity that
controls the applicant, is controlled by the applicant, or is under common control
with the applicant.
(h) Counties, cities, and towns may collect reasonable administrative fees to
implement this subsection (3) from permit applicants who are seeking to delay the
payment of impact fees under this subsection (3).
(i) In accordance with RCW 44.28.812 and 43.31.980, counties, cities, and towns must
cooperate with and provide requested data, materials, and assistance to the department
of commerce and the joint legislative audit and review committee.
(4) The impact fees:
(a) Shall only be imposed for system improvements that are reasonably related to the
new development;
(b) Shall not exceed a proportionate share of the costs of system improvements that
are reasonably related to the new development; and
(c) Shall be used for system improvements that will reasonably benefit the new
development.
(5)(a) Impact fees may be collected and spent only for the public facilities defined
in RCW 82.02.090 which are addressed by a capital facilities plan element of a
comprehensive land use plan adopted pursuant to the provisions of RCW 36.70A.070 or
the provisions for comprehensive plan adoption contained in chapter 36.70, 35.63, or
35A.63 RCW. After the date a county, city, or town is required to adopt its
development regulations under chapter 36.70A RCW, continued authorization to collect
and expend impact fees is contingent on the county, city, or town adopting or revising
a comprehensive plan in compliance with RCW 36.70A.070, and on the capital facilities
plan identifying:
(i) Deficiencies in public facilities serving existing development and the means by
which existing deficiencies will be eliminated within a reasonable period of time;
(ii) Additional demands placed on existing public facilities by new development; and
(iii) Additional public facility improvements required to serve new development.
(b) If the capital facilities plan of the county, city, or town is complete other
than for the inclusion of those elements which are the responsibility of a special
district, the county, city, or town may impose impact fees to address those public
facility needs for which the county, city, or town is responsible.
[ 2015 c 241 § 1; 1994 c 257 § 24; 1993 sp.s. c 6 § 6; 1990 1st ex.s. c 17 § 43.]
NOTES:
Effective date—2015 c 241: See note following RCW 44.28.812.
Severability—1994 c 257: See note following RCW 36.70A.270.
Effective date—1993 sp.s. c 6: See note following RCW 36.70A.040.
Severability—Part, section headings not law—1990 1st ex.s. c 17: See RCW 36.70A.900
and 36.70A.901.
SEPA: RCW 43.21C.065.
Impact fee annual report.
RCW 43.31.980
(1) Beginning December 1, 2018, and each year thereafter, the department of commerce
must prepare an annual report on the impact fee deferral process established in RCW
82.02.050(3). The report must include:
(a) The number of deferrals requested of and issued by counties, cities, and towns;
(b) the number of deferrals that were not fully and timely paid; and
(c) other information as deemed appropriate.
(2) The report required by this section must, in accordance with RCW 43.01.036, be
submitted to the appropriate committees of the house of representatives and the
senate.
[ 2015 c 241 § 4.]
NOTES:
Effective date—2015 c 241: See note following RCW 44.28.812.
Review of impact fee deferral requirements.
RCW 44.28.812
(Expires January 1, 2022.)
(1) The joint legislative audit and review committee must review the impact fee
deferral requirements of RCW 82.02.050(3). The review must consist of an examination
of issued impact fee deferrals, including: (a) The number of deferrals requested of
and issued by counties, cities, and towns; (b) the type of impact fee deferred; (c)
the monetary amount of deferrals, by jurisdiction; (d) whether the deferral process
was efficiently administered; (e) the number of deferrals that were not fully and
timely paid; and (f) the costs to counties, cities, and towns for collecting timely
and delinquent fees. The review must also include an evaluation of whether the impact
fee deferral process required by RCW 82.02.050(3) was effective in providing a locally
administered process for the deferral and full payment of impact fees.
(2) The review required by this section must, in accordance with RCW 43.01.036, be
submitted to the appropriate committees of the house of representatives and the senate
on or before September 1, 2021.
(3) In complying with this section, and in accordance with RCW 43.31.980, the joint
legislative audit and review committee must make its collected data and associated
materials available, upon request, to the department of commerce.
(4) This section expires January 1, 2022.
[ 2015 c 241 § 3.]
NOTES:
Effective date—2015 c 241: "This act takes effect September 1, 2016." [ 2015 c 241 §
5.]
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
Legislative Auditor Recommendation
The Legislative Auditor makes three recommendations to improve
efficiency and accountability of impact fee deferral programs
Recommendation #1: Legislative Auditor recommends that the cities without a deferral
program should pass an ordinance to adopt and maintain deferral programs as required
by statute.
Statute directed cities and counties collecting impact fees to establish a deferral
process for the delayed payment of those fees by September 1, 2016.
JLARC staff found that Algona, Carbonado, Deer Park, Everson, Gold Bar, Nooksack, and
Roy are collecting impact fees, but have yet to establish a deferral process for the
payment of those impact fees.
While Everson, Maple Valley, and Granite Falls report that they are in the process of
implementing a program, their city councils have not formally passed an ordinance and
adopted a deferral program into their municipal codes.
Legislation Required:
State legislation exists. Local ordinances are required.
Fiscal Impact:
JLARC staff anticipate that ordinances can be passed within existing resources.
There may be fiscal impacts from the deferrals.
Implementation Date:
June 2022
Agency Response:
Several cities and agencies formally responded and either concurred, partially
concurred, or did not concur with the Legislative Auditor's recommendations.
Responses can be found on the next pages. View the Legislative Auditor's response to City of Everson comments.
Recommendation #2: Legislative Auditor recommends the Legislature consider whether
liens are a necessary tool to ensure that deferred fees are paid.
Stakeholders report that impact fee liens add time, uncertainty, and costs to the
process. Deferral liens are likely not needed because other internal controls, like
withholding final inspection of certificate of occupancy, can be built into the
process.
Legislation Required:
Possible, depending on Legislature's determination.
Fiscal Impact:
No fiscal impact for state government.
Implementation Date:
June 2022
Agency Response:
Not applicable.
Recommendation #3: Legislative Auditor recommends that the Legislature either repeal
Commerce's data collection requirement or identify which measures Commerce should
collect for ongoing program oversight.
RCW 43.31.980 directs the Department of Commerce (Commerce) to prepare an annual
report on the impact fee deferral process. Because deferrals are not widely used and
very few issues with repayment and capital improvement have been reported, the
Legislature should consider whether Commerce should continue collecting data on
deferral use from the local governments annually.
If the Legislature wants to continue monitoring impact fee deferrals in the state,
the Legislature should revise the current list of data collected by Commerce to
include administrative costs, amount deferred, and the amount not paid on time or in
full.
Legislation Required:
Possible, depending on Legislature's determination.
Fiscal Impact:
JLARC staff anticipate that Commerce could make changes as directed within
existing resources.
Implementation Date:
June 2022
Agency Response:
AWC concurs with this recommendation. Commerce
partially concurs with this recommendation.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
AWC Response
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
Commerce Response
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
City of Everson Response
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
City of Gold Bar Response
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
City of Granite Falls Response
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
City of Nooksack Response
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
Other Responses
The Office of Financial Management (OFM) was given an opportunity to comment on this
report. OFM responded that it does not have any comments.
The Cities of Algona, Carbonado, Deer Park, Maple Valley, and Roy were also given an
opportunity to comment on this report, but did not respond.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
Legislative Auditor's Response to City of Everson Comments
I appreciate the response from the City of Everson, as well as the steps the city has
now taken to pass an ordinance adopting an impact fee deferral program.
When our study was still underway, the city noted they were in the process of
establishing a deferral program. The city has since provided an ordinance passed by
the Everson City Council showing they have established a deferral program. While the
city has adopted a deferral program, the program does not require builders to place a
lien on the property as required under current law. I consider this recommendation to
be partially implemented by the City of Everson.
Keenan Konopaski Legislative Auditor
21-05 Final Report: Impact Fee Deferral Programs
December 2021
Recommendations & Responses
Current Recommendation Status
JLARC staff follow up on the status of Legislative Auditor recommendations to
agencies and the Legislature for four years. The most recent responses from agencies
and status of the recommendations in this report can be viewed on our Legislative Auditor Recommendations page.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
More About This Review
Audit Authority
The Joint Legislative Audit and Review Committee (JLARC) works to make state
government operations more efficient and effective. The Committee is comprised of an
equal number of House members and Senators, Democrats and Republicans.
JLARC's non-partisan staff auditors, under the direction of the Legislative Auditor,
conduct performance audits, program evaluations, sunset reviews, and other analyses
assigned by the Legislature and the Committee.
The statutory authority for JLARC, established in Chapter 44.28 RCW,
requires the Legislative Auditor to ensure that JLARC studies are conducted in
accordance with Generally Accepted Government Auditing Standards, as applicable to the
scope of the audit. This study was conducted in accordance with those applicable
standards. Those standards require auditors to plan and perform audits to obtain
sufficient, appropriate evidence to provide a reasonable basis for findings and
conclusions based on the audit objectives. The evidence obtained for this JLARC report
provides a reasonable basis for the enclosed findings and conclusions, and any
exceptions to the application of audit standards have been explicitly disclosed in the
body of this report.
Committee Action to Distribute Report
On December 1, 2021 this report was approved for distribution by the Joint
Legislative Audit and Review Committee. Action to distribute this report does not
imply the Committee agrees or disagrees with Legislative Auditor recommendations.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
More About This Review
Study Questions
Click image to view PDF of proposed study questions.
21-05 Final Report: Impact Fee Deferral Programs
December 2021
More About This Review
Methodology
The methodology JLARC staff use when conducting analyses is tailored to the scope of
each study, but generally includes the following:
Interviews with stakeholders, agency representatives, and other
relevant organizations or individuals.
Site visits to entities that are under review.
Document reviews, including applicable laws and regulations,
agency policies and procedures pertaining to study objectives, and published
reports, audits or studies on relevant topics.
Data analysis, which may include data collected by agencies
and/or data compiled by JLARC staff. Data collection sometimes involves surveys or
focus groups.
Consultation with experts when warranted. JLARC staff consult
with technical experts when necessary to plan our work, to obtain specialized
analysis from experts in the field, and to verify results.
The methods used in this study were conducted in accordance with Generally Accepted
Government Auditing Standards.
More details about specific methods related to individual study objectives are
described in the body of the report under the report details tab or in technical
appendices.